Issue details
Toucan Crossing Newbridge Road
The CRSTS Bath to Bristol Strategic Corridor
(BBSC) project includes a toucan crossing at the Newbridge Road/
Old Newbridge Hill junction. Early delivery of this crossing is
proposed to be carried out by B&NES with the MCA (Mayoral
Combined Authority) supporting this early delivery. The crossing is
proposed to be constructed in August 2025 (during the summer
holidays to limit impact on the A4), with Volker’s carrying
this out under the B&NES/ Volker’s term highway
maintenance and improvement works contract. Capital funding for
this is provided by the MCA to B&NES.
Decision type: Non-key
Decision status: Approved
Notice of proposed decision first published: 22/07/2025
Decision due: 22 Jul 2025 by Director of Place Management
Contact: Paul Garrod, Team Manager - Traffic Management & Network Email: Paul_Garrod@bathnes.gov.uk Email: Paul_Garrod@bathnes.gov.uk Tel: 01225 39 4336.
Decisions
- 22/07/2025 - Toucan Crossing Newbridge Road