Temporary Accommodation Scheme (Update)
To increase the capital budget for the
development of the Temporary Accommodation Schemes (Theobald House
& Crescent Gardens) due to increased costs. These increased
costs can be attributed to a combination of: construction delay due
to emergency usage of building during pandemic; construction cost
inflation; discovery of poor ground conditions requiring piling;
and significantly improved energy efficiency measures.