Bath Quays Construction - Acceptance of Grant Offer Letter for Construction (WL)
21/08/2025 - Bath Quays Construction - Acceptance of Grant Offer Letter for Construction (WL)
(a) To agree that B&NES should accept the funding provided by the Mayoral Combined Authority and approve the spend of £3.849m to be funded from:
(1) £1.099.5m WECA Investment Funding
(2) £1.859.5m CRSTS funding
(3) £415k WECA Early Works funding
(4) £475k BANES match funding.
(b) To delegate approval to the Executive Director of Sustainable Communities, in consultation with the S151 officer, to accept the Grant Offer Letter (GOL) from the West of England Mayoral Combined Authority when it is received.