Decision details

Bath Quays Construction - Acceptance of Grant Offer Letter for Construction (WL)

Decision Maker: Cabinet Member for Sustainable Transport Delivery

Decision status: Approved

Is Key decision?: No

Is subject to call in?: Yes

Purpose:

This is a decision to instruct Volker Highways to undertake construction works for Bath Quays Links, following approval of the full business case by the Mayoral Combined Authority (WECA).

Decision:

(a)  To agree that B&NES should accept the funding provided by the Mayoral Combined Authority and approve the spend of £3.849m to be funded from:

 

(1)  £1.099.5m WECA Investment Funding

 

(2)  £1.859.5m CRSTS funding

 

(3)  £415k WECA Early Works funding

 

(4)  £475k BANES match funding.

 

(b)  To delegate approval to the Executive Director of Sustainable Communities, in consultation with the S151 officer, to accept the Grant Offer Letter (GOL) from the West of England Mayoral Combined Authority when it is received.

Reasons for the decision:

Objectives achieved as part of the project include:

 

·  Deliver priority infrastructure in Bath City Centre for pedestrians, cyclists and other non-motorised users.

 

·  Improve safety within the city centre, particularly for vulnerable users, by enhancing accessibility and reducing the potential for conflict between walking, wheeling, cycling, public transport, and private vehicles.

 

Positively contribute to a reduction in transport-related emissions, and an improvement in air quality within the city centre, helping Bath to achieve net-zero carbon by 2030.

Alternative options considered:

The alternative option is to wait until a Grant Offer Letter is received in full from the Mayoral Combined Authority (MCA). This 12-week process, in addition to the call-in period following the decision, will conclude in November 2025.

 

Following this, a six-week mobilisation period will be needed before works can start on site.

 

This will delay the construction start date until January 2026 and would further impact traffic mitigation measures planned for all other schemes due to begin construction in early 2026.

 

The final option is not to proceed. However, with allocated funding and a political commitment to deliver the scheme, it is agreed that this scheme should be progressed within the current timeframes outlined by the MCA for delivery.

Publication date: 21/08/2025

Date of decision: 21/08/2025

Effective from: 30/08/2025

Accompanying Documents: