Grand Parade & Undercroft - Viability Study
09/05/2013 - Grand Parade & Undercroft - Viability Study
(1) To NOTE the recommendations to deliver the overall project in phases as described in the attached Viability and Options report;
(2) To APPROVE a capital allocation of £5.29m for Phase 1, to be funded by Service Supported Borrowing;
(3) To DELEGATE the final decision to proceed is delegated to the Chief Property Officer, Leader of the Council, Cabinet Member for Community and Resources and the S151 Officer;
(4) To ASK the Chief Property Officer to submit planning permission for Phase 1 (developing the Colonnades and Empire Colonnades into restaurant space(s), including re-opening of the access routes from Boatstall Lane, Parade Gardens and Slippery Lane);
(5) To CONFIRM that a pre-let shall be agreed for the Phase 1 restaurant space(s) before the Council commits to construction works; and
(6) To AGREE that a licence shall be granted to a specialist market operator for Phase 2 – enhancing Bath Markets, including extending the market into the area of the Guildhall car park, and the possibility of providing planned street markets in High Street, Orange Grove and Grand Parade.