Bristol Road Chew Stoke (B3114) Provision of footway between junction with Pilgrims Way and Blind Lane
Provision of new footway is dependent upon the acquisition of privately owned residential land. Negotiations with 3 landowners commenced in 2006. Negotiations with 2 landowners have now ceased without agreement. The Cabinet Member is requested to approve the commencement of a CPO.
Decision type: Non-key
Decision status: Approved
Lead member: Roger Symonds
Lead director: Glen Chipp
Contact: Mike Widdowson, Senior Highway Engineer Email: Mike_Widdowson@bathnes.gov.uk Tel: 01225 395240.
Consultation process
Published in Weekly List 14-Oct-11
Consultees
WC PC Int LR
EFP Reference: E2296
Decisions
- 28/10/2011 - Bristol Road Chew Stoke (B3114) Provision of footway between junction with Pilgrims Way and Blind Lane