Issue details
CRSTS Canal Towpath – Bathwick Hill to Horseshoe Walk - Additional Funding
This decision is for approval of £165k
grant contribution towards the Canal and River Trust project costs
to complete the upgrade to the surface of the canal tow path
between Bathwick Hill and Horseshoe Walk. This section of the canal
towpath is a popular walkway which is in poor condition and
deteriorates further during wet weather. The plan is to improve its
surface for regular all year use. Work will be completed by June
2026.
Decision type: Non-key
Decision status: Approved
Notice of proposed decision first published: 22/04/2026
Decision due: 23 Apr 2026 by Executive Director - Sustainable Communities
Contact: Shelly Dewhurst, Waterspace Manager Email: Shelly_Dewhurst@bathnes.gov.uk Email: Shelly_Dewhurst@BATHNES.GOV.UK Tel: 01225477539.
Decisions