Ward Councillor Empowerment Fund March 2026

The current programme runs for three years (01 April 2023 - 31 March 2026)

In March 2026 eighteen project payments totalling £13,434 were approved.

From £177,000 that has been made available for the three years of this programme. As of 1st April 2026 £42,172 remained unallocated.

Submitted Applications totalling £27,934.94 have been received for projects that are awaiting processing and approval.

It therefore is anticipated that once all applications have been processed the final underspend for the programme will be £14,237.17.

Decision type: Non-key

Decision status: Approved

Notice of proposed decision first published: 09/04/2026

Decision due: 1 Apr 2026 by Executive Director - Resources

Contact: Dave Dixon, Stronger Communities Manager Email: dave_dixon@bathnes.gov.uk Email: Dave_Dixon@BATHNES.GOV.UK.