Bath City Centre Phase 1 budget uplift

The Bath City Centre Sustainable Transport Corridor will deliver infrastructure through the centre of Bath to support the adoption of active travel, with the aim of reducing car dependency. The project was initially handed over from WECA to B&NES in early 2025, with a CRSTS budget of £455k to progress design deliver a Full Business Case for the scheme.
Necessary design amends and additional work to ensure preliminary design approval have necessitated a budget uplift of £198k, which was sought from the Combined Authority and approved in July 2025. The business case was submitted to the Combined Authority for approval in September 2025.

Decision type: Non-key

Decision status: Approved

Notice of proposed decision first published: 08/12/2025

Decision due: 1 Dec 2025 by Executive Director - Sustainable Communities

Contact: Meg Collin, Project Manager Construction Email: Meg_Collin@BATHNES.GOV.UK Tel: +441225477501.