Issue details
Bath City Centre Phase 1 budget uplift
The Bath City Centre Sustainable Transport
Corridor will deliver infrastructure through the centre of Bath to
support the adoption of active travel, with the aim of reducing car
dependency. The project was initially handed over from WECA to
B&NES in early 2025, with a CRSTS budget of £455k to
progress design deliver a Full Business Case for the scheme.
Necessary design amends and additional work to ensure preliminary
design approval have necessitated a budget uplift of £198k,
which was sought from the Combined Authority and approved in July
2025. The business case was submitted to the Combined Authority for
approval in September 2025.
Decision type: Non-key
Decision status: Approved
Notice of proposed decision first published: 08/12/2025
Decision due: 1 Dec 2025 by Executive Director - Sustainable Communities
Contact: Meg Collin, Project Manager Construction Email: Meg_Collin@BATHNES.GOV.UK Tel: +441225477501.
Decisions
- 08/12/2025 - Bath City Centre Phase 1 budget uplift