Bath City Centre Phase 1 Early Works Funding ODD

Background / Reason for Decision / Purpose of Report:
Bath City Centre Phase 1 project aims to deliver walking, wheeling and cycling infrastructure to the centre of Bath, including the introduction of a cycle path which links and rationalises existing infrastructure and that being introduced by other projects. The project is funded by WECA’s CRSTS fund.
The FBC was submitted to WECA in September 2025 and a decision is expected in November 2025, with funds released following the MCA and B&NES governance process at the beginning of Jan 2026; and construction due to start March 2026. An application for Early Works Funding was submitted to WECA in September 2026 in order to:
- Commission drainage surveys in order to finalise the design, technical assurance approval (TAA) and de-risk construction programme.
- Order materials with a long (16 weeks +) lead time so as to not delay construction
- Fund enabling works being carried out as part of the Bath Quays Links project
- Carry out additional design to construction, as required for TAA approval
This funding does not affect the overall budget or scope of the project.

Decision type: Non-key

Decision status: Approved

Notice of proposed decision first published: 05/11/2025

Decision due: 5 Nov 2025 by Executive Director - Sustainable Communities

Contact: Meg Collin, Project Manager Construction Email: Meg_Collin@BATHNES.GOV.UK Tel: +441225477501.