Somer Valley Enterprise Zone Local Development Order - Commitments
The Council/LPA is promoting a Local
Development Order (LDO) at the Somer Valley Enterprise Zone (SVEZ)
to enable delivery of this long-standing employment land
allocation, via a master planning process.
This item brings forward the Future Ambitions paper which
highlights the current manifesto commitments of the Administration
and how as the SVEZ is implemented, following the adoption of the
LDO, it will seek to deliver benefits to the community over and
above planning requirement.
Decision type: Key
Reason Key: Affects more than 1 ward;
Decision status: Approved
Wards affected: Paulton;
Notice of proposed decision first published: 21/12/2023
Decision due: 1 Feb 2024 by Cabinet
Lead member: Cabinet Member for Economic and Cultural Sustainable Development
Lead director: Executive Director - Sustainable Communities
Contact: Ella Thomas, Development Officer Email: Ella_Thomas@bathnes.gov.uk.
Consultation process
The project team and its consultants have been
in regular dialogue with the landowners over the last 24 months.
The project reports into the Cabinet Member and a Key Stakeholder
Group.
An informal public engagement was held in May-June 2022 and the
formal LDO documents were published on 16th January 2023 and the
formal public consultation concluded on 23rd February 2023.
Following the initial statutory consultation, the project team
attended numerous workshops with Development Management to address
comments received and revised documents were submitted back to the
LPA. The secondary consultation began on 22nd September 2023 and
concluded on 26th October 2023
Consultees
The informal public engagement in May/June
2022 consisted of a public webinar, consultation boards in local
libraries and hard copy and online surveys. Engagement events were
undertaken at Midsomer Norton Town Council, Radstock Town Council,
Paulton Parish Council and a residents meeting in Paulton.
Both statutory consultations were hosted on the Planning Portal,
with a dedicated webpage on the B&NES site that described the
documents uploaded and then directed through to the Planning Portal
for comment. Statutory consultees were contacted directly by
Development Management to inform them of the application being
published for comment. Prior to the revised statutory consultation,
the project team attended Farrington Gurney Parish Council meeting
on the 18th September and the Somer Valley Forum on 20th
September.
EFP Reference: E3510
Decisions
Agenda items
- 01/02/2024 - Cabinet Somer Valley Enterprise Zone Local Development Order - Commitments 01/02/2024