Bath Western Riverside Phase II- Gas Rationalisation Agreement Land Transactions

Bath Western Riverside (BWR) Phase 2 is situated on the former gas works site off Windsor Bridge Road. The BWR Phase 2 site will deliver new homes and forms a central component in the Authority’s 5-year housing supply. Through the provision of Homes England Housing Infrastructure funding, the Council acquired a 1/3 land interest in the site, approximately 4 acres, and has proceeded to undertake infrastructure enabling works to unlock the site for redevelopment.

On the 29th April 2020, the Council proceeded to enter into a Gas Rationalisation Agreement (GRA) with Wales and West Utilities to relocate all live gas infrastructure to the west boundary of the site to enable the Phase 2 residential development. Practical completion of the GRA works is scheduled for September 2023 which will trigger a sequence of property related legal transactions.

This ODD seeks approval to proceed with the two, property related transactions, that are required under the GRA immediately following PC:

Decision 1: Approval is requested to proceed to purchase necessary St William land for the purpose of a Gas Governor Compound for the sum of £64,388.00 (sixty four thousand, three hundred and eighty eight pounds).
Decision 2: Approval is requested to proceed to grant a 125 year lease of the above land for the purposes of a Gas Governor Compound to Wales & West Utilities for the consideration of £10.00.

Decision type: Non-key

Decision status: Approved

Notice of proposed decision first published: 28/11/2023

Decision due: 27 Nov 2023 by Director of Regeneration & Housing

Contact: Simon Martin, Director of Capital & Housing Delivery Email: simon_martin@bathnes.gov.uk Email: Simon_martin@bathnes.gov.uk Tel: 01225 477407.

Decisions