Bath Western Riverside Phase II- Gas Rationalisation
The Council has intervened at Bath Western
Riverside via the acquisition of former gasholder operational land
and has subsequently delivered infrastructure works to unlock the
brownfield site. By drawing down Homes England Housing
Infrastructure funding, the council has the opportunity to control
the quality, pace and delivery of housing.
Considerable progress has been made on the site and the gas
rationalisation works are expected to be completed in July 2023.
Following the practical completion of the Gas Rationalisation
works, there are several legal actions which are triggered pursuant
to the Land Swap Agreement (Stage 1) dated 27th January 2022. This
includes a requirement on the Council to exercise the Option
Agreement dated 29th March 2018 to acquire the remaining land
within title ST199155 from Wales and West Utilities. The cost to
exercise the Option is £10.00.
Decision E3168 delegated authority to the Director for Economy and
Growth (now Regeneration and Housing) the power to appropriate for
planning purposes the Site (pursuant to section 122 of the Local
Government Act 1972) and to exercise the power, if required, under
section 203 of the Housing Planning Act 2016 (section 203) to
facilitate the carrying out of the development of the Site
Decision type: Non-key
Decision status: Approved
Notice of proposed decision first published: 27/07/2023
Decision due: 27 Jul 2023 by Director of Regeneration & Housing
Contact: Simon Martin, Director of Capital & Housing Delivery Email: simon_martin@bathnes.gov.uk Email: Simon_martin@bathnes.gov.uk Tel: 01225 477407.