RULE 15 Bath Quays North - Supplemental Agreement to the Development Agreement
The Development Agreement between Legal and General Development Assets Holdings Ltd and B&NES Council for Bath Quays North was entered into on 19 July 2019 and subsequently amended by Supplemental Agreement 1 on 8 October 2020.
A further supplemental agreement is now required to be entered to align approved West of England Combined Authority (WECA) funding changes, to be enacted through into the Development Agreement.
Decision type: Key
Reason Key: Significant Financial Impact and Affects more than 1 ward;
Decision status: Approved
Notice of proposed decision first published: 01/12/2020
This decision will be taken under urgency procedures.
Reason for urgency:
This item is considered under Urgency Rule 15 (Constitution 4B Access to Information Rules) to enable contracts to be awarded and works to progress to meet grant agreement programme dates as defined and approved through the WECA Change Order to Council's LGF funding agreement. To not proceed under urgency powers will risk the Council not being able to comply with these.
Decision Type: Key Decision;
Decision due: Not before 12th Dec 2020 by Council Leader
Lead director: Director of Economy & Growth
Contact: Simon Martin, Director of Capital & Housing Delivery Email: Simon_martin@bathnes.gov.uk Tel: 01225 477407.
EFP Reference: E3252