Sydney Gardens PID:
• The sum was held as a provisional item on the 18/19 capital
programme.
• The provisional item was identified following a successful
Round 1 HLF Bid for Development Phase Funding.
• Parks submitted a full Round 2 Bid to the HLF last summer
for the Delivery Phase (the provisional item on the 18/19 capital
programme).
• Planning permission and listed building consent for the
scheme was granted in October 2018
• We were successful in our R2 Bid and were awarded our HLF
grant on 12th December 2018.
Decision type: Non-key
Decision status: Approved
Notice of proposed decision first published: 23/01/2019
Decision due: 22 Jan 2019 by Corporate Director (Place)
Contact: Keith Rowe, Sydney Gardens Project Manager 01225 396383 Email: keith_rowe@bathnes.gov.uk Tel: 01225 39 6383.