1. To increase the Provisional Capital programme item for Bath Western Riverside to £44,192m to incorporate additional external funding from Homes England.

 

2.  To delegate the approval to the Director of Capital & Housing Delivery in consultation with the S151 Officer to:

 

i. Enter funding agreements with Homes England to fund infrastructure and land investment at Bath Riverside former gas lands and the Midland Road site.

 

ii. Move provisional capital approved to full approval upon entry to funding agreements and commitment to proceed on infrastructure expenditure.

 

iii. Enter back-to-back funding arrangement with St William (Berkeley Homes) to deliver site-wide remediation and infrastructure provision.