Midsomer Norton and Westfield Walking, Wheeling and Cycling Links (WL)

20/02/2024 - Midsomer Norton and Westfield Walking, Wheeling and Cycling Links (WL)

(1)  To include the Midsomer Norton & Westfield Walking, Wheeling and Cycling Links scheme as a separate project within the CRSTS programme, following the rebaselining in summer 2023.

 

(2)  To delegate authority to the Director of Sustainable Communities, in consultation with the s151 Officer, to formally accept grants from the West of England Mayoral Combined Authority relating to this scheme.

 

(3)  To approve the capital budget of £180k to develop the Full Business Case (FBC) for the scheme.

 

(4)  To agree that the provisional capital budget for the scheme is £1.25m for delivery/ construction, as reflected in the Council’s budget-setting report (February 2024).