Approval of Cycle Ambition 2 funding year 1 Kennet and Avon canal towpath improvements and cycle parking

09/11/2015 - Approval of Cycle Ambition 2 funding year 1 Kennet and Avon canal towpath improvements and cycle parking

The Cabinet Member agrees that

1)  The CAF 2 budget for 2015/16 of £655,000 is utilised for the Kennet and Avon Canal towpath improvements and £88,000 for cycle parking and to include these projects on the 2015/16 capital programme as fully approved.

2)  Cycle parking is provided throughout the authority, particularly at the main communities and around major trip generators such as high streets and libraries etc.

3)  The canal towpath between Bathampton and Sydney Gardens is improved, including widening it to 2.5 metres where space allows with it being resurfaced with a tarmac base and tar spray and  stone chip surface with appropriate signing as recommended in the CRT document “Better Towpaths for Everyone” and ongoing safety education.

4)  The section of path between the canal towpath and the railway bridge leading to Grosvenor Bridge is resurfaced with a tarmac base and tar spray and stone chip surface and appropriate signing.