Decision details
River Corridor Fund 2016-17
Decision Maker: Cabinet Member - Community Services, Cabinet Member - Homes and Planning
Decision status: Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Purpose:
Within the Council Budget approved on 16th February 2016, a capital fund of £150,000 was provisionally allocated for the River Corridor Fund 2016-17.
In order to bring forward the River Corridor Fund it is necessary to draw down against the allocated £150,000 capital funding.
Decision:
The Cabinet Members agree that £80,000 of the provisional allocation of £150,000 within the 2016/17 capital programme be allocated to three specific river corridor projects:
a. Up to £10,000 for a feasibility/viability assessment for mooring Investment on Council owned land, including Pulteney Moorings;
b. £50,000 on Strategic Flooding Project: to provide essential partner match funding towards Environment Agency Strategic Outline Business Case for major repair of Twerton gates (maintain current standard) and explore and implement improvement options at Pulteney gate; and
c. £20,000 on a Bat Habitat Strategy for River Corridor Development Sites (Bath Enterprise Area: Bath Quays).
Reasons for the decision:
The recommendation for the funding allocation has been determined through consultation with key external stakeholders including the Environment Agency, Natural England, the Canal & River Trust and the members of the Council’s Strategic River Group.
Alternative options considered:
The allocated £150,000 could have been taken as a saving or reallocated to other projects. However, these options were discounted due to two overriding factors:
· The River Corridor, Flood Risk and delivery of Bath Enterprise Area are corporate priorities set out in the Council’s Core Strategy and Green Infrastructure Strategy;
· The Strategic River Group and B&NES Placemaking Plan have highlighted these projects as priority areas for a number of the key partners (including the Environment Agency, Natural England and the Canal & River Trust).
Publication date: 10/10/2016
Date of decision: 08/10/2016
Effective from: 18/10/2016
Accompanying Documents:
- Decision E2892 River Corridor Fund 16-17 PDF 83 KB
- E2892 River Corridor Fund Capital Budget 2016-17 – Funding Allocation PDF 111 KB
- E2892z App1 Bath boat moorings review final 101213 PDF 2 MB
- E2892z App2 River Avon Options Appraisal Report Phase 1b2 Final V3 20.09.16 PDF 2 MB
- E2892z App3 Bath Flood Alleviation Scheme Options EA Sept 2016 PDF 872 KB