Leisure Dilapidation Drawdown
Decision Maker: Cllr David Dixon, Cllr David Bellotti, Cllr Paul Crossley
Decision status: Approved
Is Key decision?: No
Is subject to call in?: Yes
Purpose:
Request to draw down funds of £650K to complete concrete works before 1st July 2015
Decision:
The Cabinet Members agree that the capital budget of up to £650K to carry out significant structural concrete works at Bath Sports Centre is approved
Reasons for the decision:
The Council is responsible for all structural elements of the Leisure buildings within its portfolio and cannot pass responsibility to any Leisure operator.
Alternative options considered:
No other options are available other than to proceed with the works.
Publication date: 13/02/2015
Date of decision: 10/02/2015
Effective from: 21/02/2015