Children's Services Capital Programme 2012/13

Decision Maker: Cabinet

Decision status: Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To seek approval for capital projects to add additional capacity at primary schools required for 2013 and 2014 due to a projected increase in pupil numbers

Decision:

(1) To APPROVE the projects put forward, in line with Children’s Services capital programme priorities; and

 

(2) To APPROVE capital allocations for inclusion in the Capital Programme for projects at the following schools with phasing as shown in the report, subject, in each case, to the approval of a feasibility study;

 

Weston All Saints Primary - £1.8m

 

Castle Primary - £800k

 

Paulton Infants -£850k

 

Farrington Primary - £115k

 

St Saviour’s Junior and Paulton Junior- £30k

 

(3) To NOTE that the process of scrutiny on school planning continues to ensure an open and transparent process.

Reasons for the decision:

The projects proposed in this report are in line with intended purpose of DfE capital funding and are priorities within the Children’s Services capital programme ensuring that the Council meets its statutory duty to provide sufficient pupil places.

Alternative options considered:

The proposals reflect the most appropriate options given the areas of population growth and housing development.

Report author: Chris Kavanagh

Publication date: 06/12/2012

Date of decision: 05/12/2012

Decided at meeting: 05/12/2012 - Cabinet

Effective from: 14/12/2012