Approval of Budget for Englishcombe Lane Supported Housing Scheme

Decision Maker: Director of Capital & Housing Delivery

Decision status: Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

To approve the capital budget for the Englishcombe Lane Supported Housing Scheme for a 16-unit specialist supported housing development, as delegated by previous Cabinet decision E3633. The total Project Capital Cost is £10,881,000, including approvals to date. The anticipated Home England Grant has now been awarded and after tendering and evaluation, contract award is pending.

Decision:

To approve an additional capital budget of £10,121,000 including Homes England Grant.

Publication date: 19/12/2025

Date of decision: 19/12/2025