Bath Quays North
Decision Maker: Director of Regeneration & Housing
Decision status: Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
This decision relates the contractual
agreements for the provision of electrical infrastructure works by
utility providers at Bath Quays North (BQN). Approval is sought to
novate the “Council/Western Power Distribution (WPD), Point
of Connection agreement (PoC)” to “PowerOn Connections
Ltd (PowerOn)”.
Novation has been recommended by the Councils development partner
(L&G). The novation will allow PowerOn to have sole
responsibility for the management and co-ordination of the
electrical installation direct with WPD. The novation will also
place control of electrical supply with PowerOn.
PowerOn has been appointed by the Council for the main electrical
infrastructure works. The appointment arises through the BQN Early
Works agreement and is managed by L&G and their development
manager.
Background:
The Council has appointed L&G as its development partner for
the Bath Quays North (BQN) regeneration development. To secure the
electrical capacity for BQN, a point of connection (PoC) was
procured with WPD. During the course of 2021 and 2022, PowerOn have
been engaged by L&G to execute off site preparatory works, the
installation of a temporary substation and diversionary works
co-ordination. It is recommended that the WPD PoC agreement is now
novated to PowerOn to allow direct management control of WPD by
PowerOn.
Novation Contractual Matters.
Novation of the WPD PoC agreement to PowerOn will take place using
WPD standard terms of contract. The novation agreement has been
signed by PowerOn and requires the signatures of the Council and
WPD.
Additional assurances have been agreed between the Council and
PowerOn and recorded in a side letter agreement. The side letter
agreement is to be executed simultaneously with the
Council/WPD/PowerOn novation.
Decision:
Decision:
Novate the WPD PoC agreement to PowerOn Connections Ltd under the
WPD standard novation agreement terms.
Enter into a further side letter agreement between the Council and
PowerOn Connections Ltd.
Alternative options considered:
Alternative Options Considered:
The Council may opt to retain the WPD PoC agreement however this
will require the Council to actively manage this agreement to
co-ordinate with the PowerOn Connections Ltd works. This has been
in assessed in the pros and cons review and was considered to
present possible delay risk claims from PowerOn Connections Ltd in
the event of any misalignment in the activity of these two
organisations.
Publication date: 22/09/2022
Date of decision: 14/09/2022