Decision details
Approach Pitch and Putt Golf Course Procurement (WL)
Decision Maker: Cabinet Member for Neighbourhood Services
Decision status: Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Purpose:
Bath and North
East Somerset Council has undertaken a market engagement
exercise to both alert the market to the potential upcoming
procurement process, and to assist with the development of tender
documentation to find a new operator of the Approach Pitch and Putt
Golf Course.
There appears to be adequate interest from the supplier market to
continue with the procurement process as planned and a SMD is
required to move to Stage 2 and allocate resource.
Decision:
To move to Stage 2 of the procurement process to find a new operator for the Approach Pitch and Putt Golf Course.
Reasons for the decision:
An Engagement report was completed which summarises the responses received and recommends actions. There appears to be adequate interest from the supplier market to continue with the procurement process as planned.
The recommended procurement approach would be competition with negotiation or competitive dialogue, as there is very likely to be a need to discuss the proposals with suppliers before asking for a Final Tender Submission.
Alternative options considered:
To not proceed with the procurement and leave the site as public open space managed by parks. This has been rejected by the current administration at this time.
Publication date: 11/08/2022
Date of decision: 09/08/2022
Effective from: 19/08/2022