Decision details
Chew Valley Lake Recreational Trail
Decision Maker: Cabinet Member for Transport Services
Decision status: Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Purpose:
The construction of an off road path which
will link the trail from Woodford Lodge across the dam to the Salt
and Malt car park, through the Denny Woods picnic area towards Twy
Cross.
Decision:
The Cabinet Members agree that
1. The provisional Capital programme item for Chew Valley Recreational Trail is changed from £1,000,000 to £1,519,285.
£60,000 for 2020/21 and £1,459,285 for 2021/22.
2.
The approval to the Director of Partnership and Corporate Services
is delegated in consultation with the S151 Finance officer is
to;
i) Enter funding agreement with WECA to fund investment in the Chew Valley Recreational Trail and demonstrate compliance with the pre-commencement funding project specific conditions of WECA & Rural Payments Agency funding.
ii). Move provisional capital approved to full approval upon entry to Funding Agreements and commitment to proceed with expenditure.
Reasons for the decision:
The figure of £1,000,000 was included in the provisional Capital programme as a cost estimate for the project using the information available at the time. Since then the cost of this project has been evaluated in detail, funding bids have been awarded and the cost is now estimated at £1,519,285.
Alternative options considered:
Options for the route alignment were subject to detailed discussion with B&NES Highways, Natural England & local private land owners, to ensure along with projected costing for detailed design, construction & future maintenance the route will ensure protection of wildlife & habitat and be a route that will be attractive and safe for users, and respects the wildlife. No other viable options were identified.
Publication date: 04/02/2021
Date of decision: 04/02/2021
Effective from: 12/02/2021
Accompanying Documents:
- Decision E3250 PDF 30 KB
- E3250 CVRT PDF 110 KB
- E3250z App 1-Existing route planned and potential V4 WECA PDF 613 KB
- E3250z App 2-Planning Decision-2012 PDF 49 KB
- E3250z App 2-Planning decison 2019 PDF 93 KB
- E3250z App 3 - 25 Year Environment Plan goals PDF 116 KB
- E3250z App 4-eia_toolkit-revised_CVLRT signed PDF 251 KB
- E3250z App 5-CVLRT FBC Conditions Letter PDF 179 KB