Waste Infrastructure - Approval of Capital Expenditure

Decision Maker: Cabinet Member - Community Services

Decision status: Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To approve capital expenditure detailed in the Council's budget as a provisional item, to progress with work to relocate and modernise the Council's waste management infrastructure.

Decision:

The Cabinet Members agree that the capital budget totalling £862k is fully approved.

Reasons for the decision:

The capital sum is required in 2016/17n to enable the delivery programme for Waste Infrastructure to progress.

Alternative options considered:

Site searches and development work have been carried out on a significant number of alternative site options, which will be updated and reviewed in the context of known future circumstances.

Publication date: 24/05/2016

Date of decision: 10/05/2016

Effective from: 01/06/2016