Decision details
Project funding - Heritage Services office alteration
Decision Maker: Executive Director - Sustainable Communities
Decision status: Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
This project will make some minor
reconfiguration to offices, which will allow more staff to occupy
the space. Lighting will be upgraded to LEDs and secondary glazing
installed to improve energy performance.
Decision:
To fully approve capital amounting to
£28k from the provisional capital programme item Heritage
Services Infrastructure Development
Alternative options considered:
Do nothing: This option was rejected, the
office block is currently divided into small, randomly shaped
rooms; this configuration does not optimise the available
space.
Publication date: 10/02/2026
Date of decision: 26/01/2026
