Decision details

Bath City Centre Phase 1 budget uplift

Decision Maker: Executive Director - Sustainable Communities

Decision status: Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

The Bath City Centre Sustainable Transport Corridor will deliver infrastructure through the centre of Bath to support the adoption of active travel, with the aim of reducing car dependency. The project was initially handed over from WECA to B&NES in early 2025, with a CRSTS budget of £455k to progress design deliver a Full Business Case for the scheme.
Necessary design amends and additional work to ensure preliminary design approval have necessitated a budget uplift of £198k, which was sought from the Combined Authority and approved in July 2025. The business case was submitted to the Combined Authority for approval in September 2025.

Decision:

To fully approve the receipt of £198k of additional funding from the Combined Authority in order to deliver detailed designs and a Full Business Case for Phase 1 of the Bath City Centre project.

Alternative options considered:

To not proceed with the budget uplift, which would have limited the Council’s ability to complete the business case and proceed to delivery.

Publication date: 08/12/2025

Date of decision: 01/12/2025