Bath City Centre Phase 1 Early Works Funding ODD
Decision Maker: Executive Director - Sustainable Communities
Decision status: Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
Background / Reason for Decision / Purpose of
Report:
Bath City Centre Phase 1 project aims to deliver walking, wheeling
and cycling infrastructure to the centre of Bath, including the
introduction of a cycle path which links and rationalises existing
infrastructure and that being introduced by other projects. The
project is funded by WECA’s CRSTS fund.
The FBC was submitted to WECA in September 2025 and a decision is
expected in November 2025, with funds released following the MCA
and B&NES governance process at the beginning of Jan 2026; and
construction due to start March 2026. An application for Early
Works Funding was submitted to WECA in September 2026 in order
to:
- Commission drainage surveys in order to finalise the design,
technical assurance approval (TAA) and de-risk construction
programme.
- Order materials with a long (16 weeks +) lead time so as to not
delay construction
- Fund enabling works being carried out as part of the Bath Quays
Links project
- Carry out additional design to construction, as required for TAA
approval
This funding does not affect the overall budget or scope of the
project.
Decision:
To fully accept EWF of £701k to be spent
on drainage surveys, materials ordering, enabling works and design
for construction as early draw down from the WECA funded element of
FBC budget. This is fully funded by CRSTS grant. If there is any
delay on the grant offer letter being received from WECA, we will
use match funding as an interim measure.
Alternative options considered:
Option 1 -
To await decision of the FBC before proceeding, which brings the
risk to programme delay due to not having sufficient information or
materials to begin construction as planned. This risks the end date
of construction impeding on the 2026 Christmas embargo and on the
2027 pre-election period.
Publication date: 05/11/2025
Date of decision: 05/11/2025