Decision details

CCTV Replacement Programme

Decision Maker: Director of Place Management

Decision status: Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

The main outline of the project is to replace the System Management Platform, replace 559 CCTV camera's and install new camera's at new project sites within the Council's estate (Victoria Art Gallery). The project will also see the Council enter into a service maintenance contract with the new supplier.

Our current supplier fails the Council’s policy on transparency regarding Human Rights & Modern Slavery & can no longer be approved as a supplier of any services into the Council.
All decisions are considered through the Councils CCTV Steering Group which provides the necessary governance and oversight.

Decision:

To support Option 3 and fully approve £544k capital budget, funded by: £524k Corporate Supported Borrowing (Remaining Provisional Budget £480K, IT Replacement Budget £44K) & £20k Service Supported Borrowing (Heritage Improvement Plan)

Alternative options considered:

Option 1: Continue with existing model without current providers support.

Option 2: Purchase alternative Cameras & keep current suppliers back office system but without their support. It has been decided, running without back office system support opens us up to a number of challenges and an increased likelihood of the risk of potential downtime, complete system failure and security breaches.

Option 3: For compatibility and future technology enhancements, standardisation and requirements, the best solution is to purchase a new back office and camera solution from the same manufacturer & ensure they meet the councils policies relating to Human Rights & Modern Slavery.

Publication date: 09/08/2023

Date of decision: 09/08/2023