Meeting documents

Cabinet
Wednesday, 11th October, 2006

Bath & North East Somerset Council

MEETING:

Council Executive

MEETING DATE:

11th October 2006

AGENDA ITEM NUMBER

15

TITLE:

Building Schools for the Future: One School Pathfinder Project

EXECUTIVE FORWARD PLAN REFERENCE:

   

E

1412

WARD:

All

AN OPEN PUBLIC ITEM

List of attachments to this report:

Appendix 1 - Mace/Gleeds Report - One School Pathfinder Project

Appendix 2 - Criteria for transformation change

1 THE ISSUE

1.1 On the 15 June 2006 the DfES advised of the acceleration of the Building Schools for the Future (BSF) programme and invited the Council along with a number of other local authorities to take up funding for a one-school pathfinder project as a `down payment' on BSF with project completion required by 2009. Members agreed on 12th July to accept this offer and instructed officers to bring a report to a future meeting of the Council Executive with recommendations for the choice of pathfinder school based on the criteria set out in the DfES guidance. This report provides details of the assessment process undertaken to identify the pathfinder school and makes recommendations as to which school should be the Bath & North East Somerset pathfinder school.

2 RECOMMENDATION

The Council Executive is asked to agree that:

2.1 Writhlington School is the Council's One School Pathfinder project.

2.2 Instruct officers to notify the DfES of the chosen school and submit further details to the DfES as required to secure the necessary approval to progress the scheme.

3  FINANCIAL IMPLICATIONS

3.1 The DfES use a formula based on the planned number of pupils at the pathfinder school to determine the level of funding available from the DfES. The DfES deem that this will be sufficient to fully fund the cost of building the pathfinder school. This includes a regional location factor linked to construction costs and an inflation forecast. The DfES are proposing to fund the project by a 100% capital grant with 25% payable in 2007-08, 50% in 2008-09 and 25% in 2009-10 although precise phasing will be discussed with the DfES once the Council's proposal is agreed. Therefore there should be no cash flow or consequent interest payment impact on Bath & North East Somerset.

3.2 The DfES calculator shows that for Writhlington School the funding level would be £22.7m. However, the initial assessment undertaken by Mace/Gleeds shows that from knowledge of recent and current building projects within and outside Bath & North East Somerset, including other BSF projects in which they've been involved, construction costs would be £24.4m for Writhlington School. This leaves a potential funding shortfall of £1.7m. The DfES state that generally they will not fund above the level of the initial allocation derived by the costs calculator, however, some other local authorities have successfully negotiated an uplift in their school pathfinder allocation by establishing that their costs reflect the reality of delivering their pathfinder school. If however a funding gap remains this would be a call on the DfES formula capital allocation 2008/09 and 2009/10 which is expected to remain at the current level of £2.6m approximately per annum.

3.3 It would be an option to opt out of the scheme prior to commencement if agreement cannot be reached with the DfES regarding the level of funding required or if the funding gap could not be met from. available resources.

4 COMMUNITY STRATEGY OUTCOMES

Promoting a 'sense of place' so people identify with and take pride in our communities

Improving local opportunities for learning and gaining skills

Improving our local environment

5 CORPORATE IMPROVEMENT PRIORITIES

Improving life chances for disadvantaged teenagers

Improving the environment for learning

Improving the public realm

Improving customer satisfaction

6 CPA KEY LINES OF ENQUIRY

Ambition for the community - i.e. What the council, together with its partners, is trying to achieve

Improving engagement with and a range of services for Older People and Children and Young People

7 THE REPORT

7.1 Following the Council's decision to accept pathfinder funding it was necessary to identify the pathfinder school. The pathfinder school project must be consistent with the Authority's long term existing secondary strategy and Children and Young People Plan. In addition the chosen project must meet the following mandatory requirements.

(1) links to school improvement targets and how the project will contribute to raising standards

(2) the chosen school must have high suitability and condition need

(3) the need to provide a broad and balanced curriculum, including excellent science, design and technology facilities and PE and sports facilities

(4) the need to support an area approach to delivery of the 14-19 entitlement

(5) the extended schools/community use agenda, in line with the extended schools prospectus

(6) the need to embed the use of ICT across the curriculum

(7) the project should aim for completion and be ready for occupation by September 2009

7.2 Mace and Gleeds contractors both of whom have extensive experience in procurement and delivery of major schools projects including BSF, were commissioned to provide an objective methodology for prioritising Bath & North East Somerset's 13 secondary schools against the DfES criteria. A selection criteria matrix was devised with weightings applied to each criterion to reflect the emphasis given in the DfES guidance. Greatest weighting was given to condition and suitability need and deliverability.

7.3 Gleeds had undertaken surveys of all secondary schools in preparation for BSF and so consistency of assessment was assured. Condition scores were based on an assessment of maintenance backlog and future maintenance liabilities of each school. Suitability assesses how accommodation or lack of it impacts on curriculum delivery. e.g. classrooms too small, insufficient science labs. For both condition and suitability total value and per metre costs were taken and considered in order to ensure that higher total values (more likely in physically larger schools) did not disadvantage smaller schools.

7.4 Deliverability was assessed using a matrix which identified a range of factors which may impact on the ability of the Council to deliver within the prescribed timescale. Each school was critically assessed against each delivery risk. These included planning constraints, restrictive covenants, site conditions and access, continued operation of the school during rebuild, land ownership etc. The DfES expects the project to be completed and ready to occupy by September 2009.

7.5 The ability of the school to deliver transformational change was assessed against five key areas: Raising Standards; providing a Broad and Balanced Curriculum; 14-19 Entitlement; Extended School and Community use; use of ICT.

7.6 A copy of the Mace/Gleeds report is attached at Appendix 1. Within that report Appendix B sets out the factors considered in the Deliverability Matrix and Appendix C is the completed selection criteria matrix showing the assessment scores for all schools. It can be seen that Writhlington School achieves the highest score with 81.40 points with Ralph Allen School having the second highest score of 62.80. The majority of schools scored between 40 and 60 points. Attached at Appendix 2 are the criteria for transformational change.

7.7 The assessment showed both Writhlington and Ralph Allen schools have a high condition and suitability need and have the ability to deliver the transformational change agenda. However, with regard to deliverability, Writhlington has a much higher score than Ralph Allen.

7.8 Ralph Allen School

Ralph Allen Community School has a planned admission number of 175 and currently has 1048 on roll. The intake in year 7 in September 2006 was 178.

Advice has been sought from Planners as to the planning issues associated with developing the site. They state that "The built up part of the site is identified as a Major Existing Development Site (MEDS) in the Green Belt and the site is in the Cotswold Area of Outstanding Natural Beauty thereby meaning that development proposals are subject to restrictive planning policies".

In addition Ralph Allen occupies an undersized site compared to DfES space guidelines and is on two levels again potentially increasing the complexity of delivery whilst maintaining school provision during construction. Whilst these restrictions do not mean it would be impossible to deliver the school within the timescale it does mean it would be more challenging thus increasing the risk of increased costs and failure to complete on time. The assessment of condition and suitability identifies that approximately 25% of accommodation requires refurbishment rather than new build replacement. This presents a greater risk in that the precise nature and complexity of the works in existing buildings will not be known until further development of the proposal thus increasing the potential for delays.

Ralph Allen is the only Co-educational non-denominational Secondary school in the Greater Bath area. If it were to be rebuilt at its current size it would not require any organisational change and there would be limited impact on the other Secondary Schools in the city.

7.9 Writhlington School

Writhlington Community School has a planned admission number of 216 and currently 1154 pupils on roll. The intake in year 7 in September 2006 was 224.

Writhlington School appears to present no major barriers to delivery. Advice has been sought from Planners "It is outside the green belt and the Radstock Conservation area and is not subject to planning restrictions". It occupies a large site in excess of DfES guidelines thus presenting fewer difficulties in terms of building a new school whilst continuing in operation. Condition and suitability assessments indicate that 88% of the accommodation requires replacement; no refurbishment is required with 12% requiring refreshment (redecoration) thus reducing risk.

In the Midsomer Norton Area there are two other schools:

Norton Hill Community School with a planned admission number of 216 and currently 1325 pupils on roll. The intake into year 7 in September 2006 was 212.

Somervale Community School with a planned admission number of 168 and currently 858 pupils on roll. The intake into year 7 in September 2006 was 85.

In recent years Writhlington and Norton Hill have met or exceeded their planned admission number while Somervale has taken in less pupils than the planned admission number as a result of parental preferences. The close proximity of the three schools and the number of Secondary aged pupils (approximately 540 starting in Year 7 each year) raises issues concerning the number and size of Secondary schools in the area. Renewing Writhlington School to accommodate its current intake will enable the authority to continue to meet parental preferences in this area. However, a new school is likely to further strengthen the recent trend of high parental preferences at Writhlington School. Should Writhlington and Norton Hill schools continue to admit pupils at their current levels (450 pupils per year in the last 3 years) and total pupil numbers do not increase significantly (540 in last three years) the long term viability of Somervale School may be questioned.

7.10 The EYCL Overview and Scrutiny Panel review of Midsomer Norton/Radstock will report on the future provision of Secondary School places in this area on October 16th.

7.11 While every effort has been made to provide an objective methodology for each of the criteria there is inevitably a degree of subjectivity both in terms of the weighting applied and the detailed decisions made within each category. However the engagement of Mace and Gleeds has as far as possible provided an objective view.

7.12 The assessment process has identified Writhlington School as the school which best meets the DfES criteria for pathfinder status and Members are recommended to agree this school as the Council's One School Pathfinder project.

8 RISK MANAGEMENT

8.1 The report author and Lead Executive member have fully reviewed the risk assessment related to the issue and recommendations, in compliance with the Council's decision making risk management guidance.

8.2 As set out in Section 7 above and as evidenced in the Mace/ Gleeds report risk has been a key factor in identifying the preferred pathfinder school. The recommendation reflects the assessment that Writhlington School offers the lowest risk option for delivering a school within budget and achieving the required timescales for delivery.

8.3 As identified in Section 3 there is a possibility that there may be a funding gap between the DfES funding and the estimated construction costs. Any shortfall would be a call on the DfES formula capital allocation 2008/9 and 2009/10 thus reducing the scope to undertake medium sized improvement projects at other schools. There is a risk that actual outturn costs may exceed funding available. This risk will be mitigated by the selection of Writhlington School which presents the least risk in term of delivery and by detailed briefing of the project and strong project management, particularly in the early stages when the detailed cost plan is developed.

8.4 There is a risk that the new school will take its full intake of pupils (as Writhlington has done for several years) bringing into question the long term viability of Somervale school.

9 RATIONALE

9.1 The assessment process has identified Writhlington School as the school which most closely meets the DfES mandatory criteria and offers the least risk.

10 OTHER OPTIONS CONSIDERED

10.1 The assessment process undertaken considered the needs of all secondary schools set against the DfES criteria. The assessment has shown that Writhlington School best meets these criteria.

11 CONSULTATION

11.1 Overview & Scrutiny Panel; Lead Executive Member; Stakeholders/Partners; Section 151 Finance Officer; Chief Executive; Monitoring Officer.

11.2 There has been no formal consultation on this proposal although Headteachers and other partners have been kept informed of the process. Following selection of the school there will be consultation with the school and the wider community about the building of the new school as required by the DfES.

12 ISSUES TO CONSIDER IN REACHING THE DECISION

12.1 Social Inclusion; Sustainability; Property; Young People.

13 ADVICE SOUGHT

13.1 The Council's Monitoring Officer (Council Solicitor) and Section 151 Officer (Strategic Director - Support Services) have had the opportunity to input to this report and have cleared it for publication.

Contact person

Chris Kavanagh, Schools Capital and Organisation

01225 395149, chris_kavanagh@bathnes.gov.uk

Background papers

DfES `Building Schools for the Future: One School Pathfinder' guidance document 15th June 2006

Please contact the report author if you need to access this report in an alternative format