Meeting documents
Cabinet
Wednesday, 5th October, 2005
Bath & North East Somerset Council |
|||||
MEETING: |
Council Executive |
||||
DATE: |
On 5 October 2005 |
PAPER NUMBER |
|||
TITLE: |
Bath Communities Partnership Southside Youth and Community Centre Redevelopment Feasibility |
EXECUTIVE FORWARD PLAN REFERENCE: |
|||
EWP |
01109 |
SU |
|||
WARD: |
Southdown, Twerton |
||||
AN OPEN PUBLIC ITEM |
|||||
List of attachments to this report: Southside Youth and Community Centre Redevelopment Pre-Feasibility Report |
1 THE ISSUE
1.1 Consideration of a proposal from Bath Communities Partnership to redevelop Southside Youth & Community Centre into a community resource centre, providing offices, training and conference facilities, youth provision, recreational facilities and managed workspace.
2 RECOMMENDATION
2.1 The Council Executive is recommended to:-
2.1.1 Consider the proposal from Bath Communities Partnership (attached) to undertake a detailed feasibility study for the re-development of the Southside Youth and Community Centre.
2.1.2 Take account of their resolution at the Executive meeting on 7th September 2005 "To agree to defer any additional spending on capital schemes unless there is certainty around funding sources for those works".
2.1.3 Note that the proposal from Bath Communities Partnership identifies a need for both capital and revenue funding from the Council.
2.1.4 Either
·Support the principle of redevelopment of the Southside Youth & Community Centre subject to detailed feasibility and the necessary resources being identified by Bath Communities Partnership, OR
·Conclude that the additional finance cannot be met from the Council's own resources and leave BCP to develop alternative proposals for use of the remaining South West of England Regional Development Agency (SWERDA) funding.
3 FINANCIAL IMPLICATIONS
3.1 The costs of a detailed feasibility study would be met by
the Bath Communities Partnership and financed by the South West
England Regional Development Agency. The proposed feasibility study
would examine the Capital and Revenue costs in detail to form a
view of the overall financial stability of the proposed project. It
would include both a demolish and rebuild option as well as a
refurbishment option.
Capital cost
3.2 Representatives from SWERDA have advised BCP that the
estimated cost for redevelopment of the centre could total
approximately £1.2 Million excluding the cost of the site.
The BCP could contribute £500,000 towards this project using
SWERDA funding and a further £100,000 has been pledged by a
Charitable Trust. The balance of £600,000 remains unfinanced.
Sources of potential funding for this sum include:-
·Private business Investors
·Charity bank
·Community investment fund
·Council Capital budgets
·Section 106 contributions from local development
·Private sector Managed workspace provider (with potential
SWERDA support)
3.3 The site is valued at approximately £300,000. Were the
project to go ahead, the Council would make a further contribution
of this amount by transferring the site to a Development Trust
supported by legal status registering with Companies House as a
Company Limited By Guarantee on a Freehold or long lease
basis.
Revenue (ongoing) cost
3.4 The operating costs and potential income generation for the new facility have been subjected to an initial, high level review. This review indicates that operating costs- including utilities and building maintenance- could total approximately £66,000 per annum, whilst external rental income of £44,000 per annum could be achieved by letting office managed workspace and the reminder of the building.
3.5 A further contribution could be obtained following the
transfer of Youth and Community Services into the facility,
although this may require additional revenue finance by the
Council, if it does not produce a reduction in costs elsewhere
within the Youth and Community Service.
3.6 Members should note that the Councils existing capital
programme has made no provision for either the capital or ongoing
revenue costs of this project. The Executive agreed on 7th
September 2005 - "To agree to defer any additional spending on
capital schemes unless there is certainty around funding sources
for these works".
3.7 The Councils capital programme remains over-committed and it
is advised that no further unfunded additions should be made to the
existing programme. Members could decide to proceed to detailed
feasibility stage but any proposals that require capital funding
from the Council will prove extremely difficult in the current
capital planning context.
4 THE REPORT
4.1 This report considers a proposal from Bath Communities
Partnership to undertake a detailed feasibility study for the
redevelopment of the Southside Youth & Community Centre and
requests that the Council gives it "in principle" support to such a
scheme if it can be proved viable. The attached report from Bath
Communities Partnership gives more details on the
concept.
4.2 In developing the concept so far, Bath Communities
Partnership has consulted stakeholders such as the Primary Care
Trust; The Princes Trust; Bath Racial Equality Council; South West
Bath Credit Union and Jobcentre Plus, all of whom have given their
broad support for the concept. A detailed feasibility study would
include wider consultation with the communities which the
regeneration scheme is aiming to support - the Black and Minority
Ethnic communities across Bath and the residential communities of
the South West Triangle (Twerton Ward, Southside Ward and a part of
Westmoreland Ward).
4.3 If the feasibility study led to a viable project proposal,
this would be subject to a SWERDA led appraisal process, ensuring
that the project was meeting relevant objectives and statutory
requirements such as the Race Relations Act Amendment.
4.4 The Southside Youth & Community Centre belongs to the
Council. The building was put up in 1967 as a Youth and Community
Centre primarily to support the new community on the Whiteway
Estate and surrounding area. An extension was built onto the
Community Centre arm of the building in the mid 1980's as a lounge
and skittle alley, for what was effectively a social club. The
building has been run almost from it's inception as two separate
parts. One part of the building is the Youth Centre where Youth
Activities are run for 3 evenings a week, approximately 3 hours per
evening, and a programme of youth activities are organised by the
worker for young people on the estate at other times, often
including weekends. This includes using the outside sports court
for a range of sports activities both formal and informal. A
full-time youth worker is based at the club along with part-time
youth support staff, covering youth support in the Bath South area.
A range of playschemes and activities are run every holiday period
in association with Bath Area Play Project, and by the youth work
staff including residential activities and 'community fun days'.
The playschemes are for 2 weeks at Easter and for 3 weeks in the
Summer. The Youth Centre/staff ran until 2004 a project during the
day, for excluded and at risk of exclusion pupils from across the
authority, but because of the state and access to the building that
project stopped, and has been developed elsewhere.
4.5 The use of the both parts of the building has suffered over
the last four years primarily because of the very poor state of the
Community section, and because of the very poor access, for which
major DDA work is required. The Youth Centre was regularly used for
community activities and meetings including as a base for the
Southside Community Association and the Southside Food
Co-operative, up until the last 18 months. Currently other than the
day use by the Holiday Playschemes, the building is used for
Councillor Advice surgeries, an arts project (ACTA), and for
occasional meetings; for approximately 3 hours per week. The
Community half has been empty, unused and in very poor condition
for four years since the previous leaseholder left , with major
work needed to make it sound and usable for the public. In November
2003 the Youth and Community Service within the Council
commissioned a feasibility study for refurbishment of the building,
and the costs were then estimated at about £500k, and a
number of other options for partial development have been explored,
but the funding needs are considerable.
4.6 The long term regeneration benefits of this project could be
substantial, providing a positive focus for a community which by
most indicators is the most deprived in Bath and North East
Somerset. It attempts to provide better access to services such as
Youth provision and outreach services from the Primary Care Trust
and Jobcentre Plus. It also aims to promote the economic
regeneration of the area by encouraging entrepreneurs and creating
jobs within the managed workspace element. If proven to have long
term financial stability it has the potential to be an effective
way of supporting a holistic approach to regeneration. Whilst the
potential direct benefits for residential communities in the area
are clear, more evidence on the positive impact the proposal would
have on the city's Black and Minority Ethnic Communities would need
to be demonstrated.
5 RISK MANAGEMENT
A risk assessment related to the issue and recommendations has been undertaken, in compliance with the Council's decision making risk management guidance.
6 RATIONALE
6.1 The Bath Communities Partnership is in the final year of a
regeneration programme funded by the South West Regional
Development Agency. The Partnership has been making good progress
with achieving the outcomes and outputs it was contracted to
achieve. The Partnership has approximately £500,000
unallocated within its programme and has been considering the most
appropriate options to invest this money and leave a lasting
regeneration impact. The redevelopment of the Southside Youth and
Community Centre has emerged as an idea to help achieve long
lasting regeneration in the area and the Partnership has undertaken
a pre-feasibility report which they have submitted to the Council.
The South West Regional Development Agency is content for the
Partnership to undertake more detailed feasibility if the Council
commits its "in principle" support. A new development trust or
other community controlled legal entity would be formed to lead
this project if it were proved to be feasible.
7 OTHER OPTIONS CONSIDERED
7.1 BCP and SWERDA have considered other options for investing
the £500,000. The Partnership is developing these options but
the redevelopment of the Southside Youth & Community centre
remains their preferred option. In the Partnership's view, their
proposal offers the best opportunity to support its target groups
and support long term social and economic regeneration. Alternative
projects will be more strictly related to economic development
criteria in compliance with SWERDA.
7.2 The Council could at this stage reject the proposal if it
felt it would not achieve a lasting regeneration impact or if any
additional finance required could not be met from the Council's own
resources.
8 CONSULTATION
8.1 Ward Councillors, Other B&NES Services, Section 151 Finance Officer, Chief Executive, Monitoring Officer
8.2 Circulation of draft Executive report and Bath Communities
Partnership proposal
8.3 Ward members for Southdown and Twerton have expressed their support for the project in concept and for a feasibility study to be undertaken.
9 REASONS FOR URGENCY
Contact person |
Bill Cotton - 01225 477295 |
Background papers |
Bath Communities Partnership pre-feasibility study |