Meeting documents

Cabinet
Wednesday, 4th February, 2004

CORPORATE PLAN

2003 - 2007

1

LIST OF CONTENTS

1 LIST OF CONTENTS 2

2 GLOSSARY 4

3 EXECUTIVE SUMMARY 5

3.1 Introduction 5

3.2 Improvement Priorities 5

3.3 Strategies for creating financial and organisational headroom and capacity to achieve this Plan 5

3.4 Risk and constraints 6

3.5 Financial Strategy and Financial Plan 6

3.6 Implementation Plan 7

3.7 Monitoring and review of the Corporate Plan 7

4 INTRODUCTION 8

5 NATIONAL, REGIONAL, LOCAL AND FUTURE ISSUES 8

5.1 National issues 8

5.2 The Community Strategy, regional and sub-regional issues 8

5.3 Local issues 9

5.4 Future issues 9

6 IMPROVEMENT PRIORITIES 10

6.1 Developing Improvement Priorities 10

6.2 Improvement Priorities 10

6.2.1 Increase Availability of Affordable Housing 10

6.2.2 Promoting the Independence of Older People 11

6.2.3 Reducing the Fear of Crime 11

6.2.4 Improving the environment for learning 12

6.2.5 Improving the life chances for disadvantaged teenagers, through improvements to their education, training and support 12

6.2.6 Improving the Quality of Public Transport, Roads and Pavements and Easing Congestion 13

6.2.7 Reducing landfill 13

6.2.8 Improving the urban public realm (`liveability') 14

6.2.9 Improve Customer Satisfaction 14

6.2.10 Develop a sustainable economy for Bath and North East Somerset 15

7 STRATEGIES FOR CREATING FINANCIAL AND ORGANISATIONAL HEADROOM AND CAPACITY 15

7.1 Organisational Improvement Actions 17

7.2 Risks and Constraints 17

7.3 Financial Strategy and Financial Plan 18

7.4 Implementation Plan 21

8 MONITORING AND REVIEW OF THE CORPORATE PLAN 21

8.1 Key performance indicators 21

8.2 Key targets for services 21

9 LIST OF APPENDICES 23

APPENDIX 1 - IMPROVEMENT PRIORITY PLANS 24

APPENDIX 2 - FINANCIAL PLAN COMMENTARY 40

Annexe 1 - Capital Planning 2005/06 & 2006/07 42

Annexe 2 - Revenue Financial Planning Targets 43

2 GLOSSARY

BESD

Behavioural, Emotional & Social Difficulties

BSF

Building Schools for the Future

CCTV

Closed Circuit Television

CIS

Community Information Service

Community Resource Centre

Referred to in the Framework document as Elderly Peoples Homes (EPH's)

CPA

Comprehensive Performance Assessment

CVS

Community & Voluntary Services

DAT

Drug Action Team

DCMS

Department for Culture Media & Sport

DfES

Department for Education & Skills

FSS

Formula Spending Assessment

HR

Human Resources

KPI

A Key Performance Indicator (KPI) is a measure of Council performance which makes a significant contribution to the Council's improvement priorities and warrants immediate investigation if it is not being achieved.

KS3 & 4

Key Stage 3 and 4

LBSS

Locality Based Support for Schools

LEA

Local Education Authority

LSC

Learning Skills Council

LSC

Learning Skills Council

LSP

Local Strategic Partnership

MSN

Midsomer Norton

NEET

Not in Education, Employment or Training

PCT

Primary Care Trust

PRU

Pupil Referral Unit

PSA

Public Service Agreement

SARI

Support Against Racist Incidents

SEN

Special Educational Needs

UNESCO

United Nations Educational, Scientific & Cultural Organisation

3

EXECUTIVE SUMMARY

3.1 Introduction

This document populates the Corporate Plan Framework (published and approved in November 2003) with the key actions and targets that need to be achieved to enable the Council to realise its Community Strategy, Improvement Priority, performance and financial objectives. The issues that informed the development of these actions and targets were well documented in the November framework and are not repeated in full here

(see http://intrasrv/intranet/committee_papers/Council/co031120/10zannex.htm).

The adoption of this, the Council's full Corporate Plan, is a result of merging the Framework document (approved November 2003) with this more detailed Plan. When Council approves this Plan in February 2004, it will be made available in summary format to allow effective communication of the Council's plans and Improvement Priorities to all employees in the organisation, the public and key partners.

3.2 Improvement Priorities

In the framework document approved November 2003, Council agreed a set of eight "community-focussed" improvement priorities together with four "organisational" (or internal) ones. Improvement Priorities are those issues and consequent activities upon which the Council decides to focus its energy and resources, in order to ensure that overall Council objectives are achieved.

In developing the action plans, it was determined that it is unhelpful to distinguish between "community focussed" and "organisational" Improvement Priorities and so a single set of ten Improvement Priorities is now proposed. These are supported by an integrated set of organisational actions necessary to provide the capacity and infrastructure to ensure delivery and achievement of the Improvement Priorities. Section 6.2 is structured around this proposal.

The Improvement Priorities are:

B7 Increase availability of affordable housing

B7 Promoting the independence of older people

B7 Reducing the fear of crime

B7 Improving the environment for learning

B7 Improving the life chances for disadvantaged teenagers, through improvements to their education, training and support

B7 Improving the quality of public transport, roads and pavements and easing congestion

B7 Reducing landfill

B7 Improving the urban public realm (`liveability')

B7 Improve customer satisfaction

B7 Develop a sustainable economy for Bath and North East Somerset

3.3 Strategies for creating financial and organisational headroom and capacity to achieve this Plan

The resources (e.g. money, time) needed to achieve the outcomes of the Improvement Priorities will not materialise by themselves. Through the Corporate Plan strategies have therefore been devised to create the financial and organisational headroom and capacity needed to ensure that resources can be directed towards its priorities. These strategies involve:

· The release of funding as a result of improved productivity or income generation (service standards should remain broadly the same, but costs will be reduced)

· creating greater organisational flexibility (quicker response, adaptability to change, "can-do" culture etc)

· the introduction of sustainability practices as one of the means by which the Council can achieve organisational shift and headroom, increasing capacity through the more efficient use of resources.

Successfully achieving these strategies will create headroom and capacity without significant reductions in service levels. Given the timescales available to develop and implement these strategies and the need to target resources most effectively, it should be recognised that it will also be necessary to consider the redirection of funding from other services, which may involve the diminution of service scope or standards.

3.4 Risk and constraints

The Council does not operate in isolation - neither is everything certain to go according to plan and it is important to recognise from the outset the risks and constraints upon this Plan. Each year the Council carries out risk assessments to identify key risks facing the Council and the actions needed to manage those risks.

The most recent risk assessment highlighted the following top three risks:

· Service cost escalation undermining prioritisation

· Exposure to financial liabilities arising from risks on major development projects

· Government demands competing with local initiatives resulting in capacity overload and failure to deliver

To manage these risks a number of mitigation actions and strategies have been implemented.

3.5 Financial Strategy and Financial Plan

The Corporate Plan Framework Document put forward a financial strategy in order to focus resources on the Improvement Priorities alongside a target to set annual Council Tax rises in line with the government guideline. The main points of the financial strategy required over the period 2003 - 2007 to achieve these aims were as follows:

· Financial headroom will be allocated towards the Improvement Priorities and linked to achievement of specific results

· For all services provided by the Council, clear financial planning targets will be set; Service Plans will link performance targets to required levels of resources, identifying the requisite workforce planning, IT and accommodation needs

· Financial targets for education and social services will, over time, reflect a tempering of the rate of growth so that the gap between spending and the government's norm (FSS) is narrowed; this will enable local income to be seen to assist local priorities

· In order to create financial headroom, revenue funding will be released within the organisation through greater productivity and some revenue funding will be redirected from other services resulting in more revenue flexibility being achieved by 2005

· Capital expenditure will be used, only where thoroughly justified, to help fund Improvement Priorities and to invest in productivity improvements which create future years' revenue headroom. Asset-holding will be reviewed in order to ensure best use of resources whilst borrowing is likely to be the principal source of finance for additional capital spending in the short- to medium-term

· Capital expenditure will also be used, again only where thoroughly justified, on a commercial basis, to increase investment to assist the sustainability of the Council's key income streams - notably its commercial estate, museums and car parks

· Recognising that it has very limited funds, the Council will actively seek external funding, especially for schemes that fit Improvement Priorities

B7 Recognising inherent financial risks, the Council will continue to build balances over time to a level which matches its risk assessment (see 93risks and constraints94 above); active management of budgets will continue to ensure financial control and avoid budget pressures and overspending subverting the overall Corporate Plan.

Following the approval of the Corporate Plan Framework Document, a Financial Plan for the period 2004/05 - 2006/07 has been devised, based on the above financial strategy. This is detailed at section 7.

3.6 Implementation Plan

The Corporate Plan document of itself will not deliver improvement. To deliver improvement it is intended that the Plan will be developed and implemented through a series of phases extending to May 2007. These phases are detailed at section 7.4.

3.7 Monitoring and review of the Corporate Plan

Key Performance Indicators (KPIs) will be used to ensure that any deviation from our plans to implement improvement priorities is highlighted so that prompt corrective action can be taken KPIs will supplement existing performance measurements so that priorities for action can be set. The Council's existing performance management framework has been recognised by external inspectors as an excellent system, and we intend to maintain this strength.

4

INTRODUCTION

This document populates the Corporate Plan Framework (published and approved in November 2003) with the key actions and targets that need to be achieved to enable the Council to realise its Community Strategy, Improvement Priority, performance and financial objectives. The issues that informed the development of these actions and targets were well documented in the November framework and are not repeated in full here

(see http://intrasrv/intranet/committee_papers/Council/co031120/10zannex.htm).

Completing this, the Council's first Corporate Plan, marks the beginning of a new process which over time will link the Council's focus on priorities, services delivery, resource and finance plans together. Achieving this objective requires the Council to plan and do things differently. Significant progress in developing plans has been made in a very short space of time and lessons learned are being developed to improve processes for the annual review of the Corporate Plan, which begins in autumn 2004.

The purpose of reviewing the Corporate Plan is to take account of changing circumstances, ensuring that the targets in it are still appropriate and that resources are in place to deliver those targets. Service Plans and the annual Best Value Performance Plan will provide the detail of what is to be delivered year by year and the framework for monitoring performance will continue to develop.

The adoption of this, the Council's first Corporate Plan, is a result of merging the Framework document (approved November 2003) with this more detailed Plan. When Council approves this Plan in February 2004, it will be made available in summary format to allow effective communication of the Council's plans and Improvement Priorities to all employees in the organisation, the public and key partners.

5 NATIONAL, REGIONAL, LOCAL AND FUTURE ISSUES

5.1 National issues

The national issues identified as having an effect at local level highlighted in the Corporate Plan framework document such as perceived levels of crime, health services, decent affordable housing and transport issues (such as public transport and reducing levels of traffic congestion) are being addressed as part of specific improvement priority action plans. Broader issues which have an effect at national and local levels include sustainability issues such as climate change policies and legal regimes governing waste disposal.

5.2 The Community Strategy, regional and sub-regional issues

Bath and North East Somerset's Community Strategy (Strategy) was approved by the Council and Local Strategic Partnership (LSP) in November 2003. The Strategy sets out a series of ambitions for the area over the next ten years, as well as a framework for how these can be delivered through partnership working. For each ambition, there is a series of indicators by which success can be measured, as well as a set of key early actions to unlock improvement. This Corporate Plan includes actions the Council intends to take to help deliver the Community Strategy over the coming four years.

The Strategy was developed through extensive consultation with local communities using an inclusive approach called "Be Better for Everyone". This involved a series of community road shows and other consultation events designed to encourage local communities to come forward with their views. Postcards and websites were also used to ensure there were plenty of opportunities for people to have their say.

The Community Strategy seeks to address key issues for the Bath and North East Somerset area, many of which can only be tackled through partnership working, often at sub-regional and regional levels. For example, the Corporate Plan Framework document approved in November 2003 identified house price to income ratios and skills levels as particular issues for this region. At a sub-regional level, Bath and North East Somerset has three structural issues - Housing, Transport and Skills shortage - which the Council does not have the capacity to resolve on its own. Improvement in these areas will require the Council to invest in partnership working with other organisations, local and national government agencies.

The Community Strategy identifies early actions which LSP members will contribute towards, in order to address these issues. Examples include, on the issue of affordable housing, LSP partners will facilitate the Health Key Workers Housing Partnership and support the National Housing Federation campaign to make the case for additional funding for affordable housing in the South West. Other actions include finding ways to improve recruitment and retention of staff and working to ensure a better understanding of the role of the Local Plan in promoting sustainable development.

The Council will work closely with partners to contribute to the ambitions contained in the Strategy. Actions include developing our Citizenship in Action project to link more closely with young people, reviewing and improving the accessibility of services to disabled people and the accessibility of information and services in community languages, including translation and interpretation services'.

In particular, the Council will focus on improving the effectiveness of its partnership working so that the Community Strategy's ambitions can be delivered and will work with others to establish effective key partnerships for Transport and Culture, encouraging partnerships to work together to promote the "liveability" agenda which includes tackling litter, graffiti and anti-social behaviour.

The Council's Improvement Priority and service plans detail further actions to contribute to resolving these issues.

5.3 Local issues

Issues at local level that reflect national issues and which the authority can progress include concerns about community safety, facilities for youth, cleanliness of the environment, local industry, jobs and the consequences of an ageing population. Actions the Council will take in regards to these issues are detailed in Improvement Priority and service plans.

5.4 Future issues

Future issues are those things the Council needs to be aware of in developing any long term plans. Many are documented in the Council's key plans and strategies and include the increasing focus on more joined up Health and Social Services provision, the future effects of the ageing population on the local economy, single status in employment and advances in technology and communications, environmental factors such as the issue of waste disposal, lack of available affordable housing and threats to the local economy from international disasters such as September 11th.

The achievement of the Community Strategy and Improvement Priority action plans is expected over time to make a significant contribution to ensuring that future issues can be managed. Actions range from further joint working between the Councils own Social Services and the Primary Care Trust on health care services particularly for the more vulnerable people in our society, to using technology to improve access to services and increasing the availability of affordable housing. Other initiatives such as the development of the Waste Environment Park are all designed to mitigate the impact of issues already identified as possible threats to the economy and viability of Bath and North East Somerset.

Work to identify and plans to address future issues will continue to be a part of the activity that underpins the development of this Plan.

6 IMPROVEMENT PRIORITIES

In the framework document approved November 2003, Council agreed a set of eight "community-focussed" improvement priorities together with four "organisational" (or internal) ones. Improvement Priorities are those issues and consequent activities upon which the Council decides to focus its energy and resources, in order to ensure that overall Council objectives are achieved.

Since November, proposed actions have been developed for each Improvement Priority, led in each case by a "sponsor" Executive Member and Director.

In developing the action plans, itwas determined that it is unhelpful to distinguish between "community focussed" and "organisational" Improvement Priorities and so a single set of ten Improvement Priorities is now proposed. These are supported by an integrated set of organisational actions necessary to provide the capacity and infrastructure to ensure delivery and achievement of the Improvement Priorities. Section 6.2 is structured around this proposal.

6.1 Developing Improvement Priorities

The development of the statedImprovement Priorities was informed by a number of sources including:

· CPA priorities in the CPA Improvement Plan

· Improvement ambitions identified in the Community Strategy

· PSA targets as shown in the Best Value Performance Plan 2003-04

· Press and media - identified through research that informed the Overview & Scrutiny work plan 2003 and confirmed as being still topical May 2003

· Performance indicators and customer satisfaction results: 3rd and 4th quartile performance indicators 2001-02 (actual performance).

· Voicebox Surveys

· National priorities as identified by national surveys (e.g. MORI research report "The rising prominence of liveability, or are we condemned to a life of grime?" September 2002)

Sections 3 to 5 of the Corporate Plan Framework document approved by Council in November 2003 (http://intrasrv/intranet/committee_papers/Council/co031120/10zannex.htm) set out further background and context.

A consistent theme which needs to be noted and that is common throughout the detailed action plans, is that for the Council to be successful in achieving its Improvement Priorities, the Council must work in partnership with others.

Further information on the actions planned to be taken in regards to the Improvement Priorities is shown at Appendix 1.

6.2 Improvement Priorities

For each Improvement Priority, the text below sets out the Council's goal for achievement by 2007, existing initiatives which are already realising improvement, further actions now planned and related initiatives from individual Service Plans. Summary financial information is also highlighted in the appendix.

6.2.1 Increase Availability of Affordable Housing

An overall increase in the amount and range of affordable housing is a long term goal (10-20 years) requiring some large and far reaching decisions e.g. in relation to spatial planning, housing density and resource allocation. By 2007 we will have established and be working on an affordable housing strategy that will be complemented by an agreed Local Plan, which will enable the Council to identify proactively suitable residential sites and work with a range of partners to develop a variety of housing tenures. It is envisaged that in the lifetime of this Corporate Plan, actions undertaken will seek to minimise the growing gap between affordable housing and demand/need.

Initiatives already underway to achieve this improvement priority include completing a 6 year investment strategy to build 600 new homes by the end of 2005, a target of 30% minimum affordable housing as part of the Western Riverside project, work with Bath University and Bath Spa University College to manage student housing needs and work with the Local Strategic Partnership to develop key worker housing by bidding for additional funds at regional level.

Further actions we plan to take to achieve this improvement priority include developing an affordable housing strategy to optimise the potential for affordable housing in the area by setting out clear, agreed priorities for action and investment. Plans are being developed to optimise the use through the planning system of contributions to affordable housing from developers, by ensuring that affordable housing is a key feature within the Local Plan. The Council is also managing the development of additional extra-care affordable housing as part of its provision of three Community Resource Centres for older people, to achieve an increase in affordable housing options for older people.

Service plan developments that underpin this improvement priority include encouraging public service employers to develop innovative approaches to meeting the current & future housing needs of their staff through the Community Strategy, reducing the use of Bed and Breakfast accommodation and developing frameworks for improvements across Keynsham, Midsomer Norton and Radstock Town Centres.

6.2.2 Promoting the Independence of Older People

By 2007 we are aiming jointly with the Primary Care Trust and other NHS Providers to deliver services in an integrated and timely way that will promote, retain or restore the maximum level of independence possible for individuals, with the least intervention necessary (i.e. the right service, in the right place, at the right time).

Initiatives already underway to achieve this improvement priority include improving speed of response in assessing the needs and provision of services to more vulnerable older people and joint working with the Primary Care Trust and voluntary sector partners to devise a whole system approach to older peoples care.

Further actions to achieve this improvement priority include helping more, older people, to remain in or return to their own homes following hospital admission by regaining and / or improving their independent living skills by reconfiguring the home care service. The Council will also work to ensure a flexible approach to transport to provide for the needs of older people encouraging greater use of public transport through provision of Dial-a-Ride schemes, concessionary fares and supported bus services.

Service plan developments that underpin this improvement priority include reducing the number of delayed discharges from acute beds attributable to Social Services by improving intermediate care services, providing an efficient single assessment process for older people and increasing the number of people in all client groups receiving a direct payment in lieu of services which will promote independence of older people through offering more choice and control.

6.2.3 Reducing the Fear of Crime

Working closely with our partners in the Community Safety Partnership such as the Police, we aim by 2007 to increase public confidence and see a reduction in the fear of crime. This will be achieved by the Partnership improving and maintaining the public environment or `street scene', reducing the level of vehicle crime and burglaries and by working positively in a preventative way with young people to avoid their involvement in youth crime and disorder.

Initiatives already underway to achieve this improvement priority include implementing a vehicle crime action plan, Community Warden Scheme (which we will keep under review, together with police schemes), graffiti removal schemes, litter and cleansing enforcement, incremental change in the expansion of street lighting and support for voluntary organisations including Victim Support and Support against Racist Incidents (SARI).

Further actions to achieve this improvement priority include supporting a range of initiatives for people who may be more vulnerable to crime or fear of crime including older people, black and ethnic minority communities, disabled people and survivors of domestic abuse and develop and implement an anti social behaviour action plan to ensure a rapid response to incidents of anti social behaviour.

Service plan developments that underpin this improvement priority range from drawing up a management plan for Abbey Churchyard Bath in partnership with local stakeholders and providing a security presence at Parade Gardens, to introducing a Town Ranger scheme for Norton Radstock, enforcing litter fines and implementing Council responsibilities in regards to the new Licensing Act 2003, aimed at preventing crime and disorder, improving security in car parks, safe guarding public safety, preventing nuisance and protecting children from harm.

6.2.4 Improving the environment for learning

By 2007 we aim to have secured additional capital to invest in improving the quality of learning in classrooms and schools. This, together with more effective management of capital resources, will also enable us to meet our Schools' Asset Management Plan targets and ensure sufficient resources to successfully implement changes arising from area reviews.

Initiatives already underway include securing maximum capital available through Government initiatives - recent successes include Targeted Capital Grant and Teaching Environments for the Future, securing developer contributions through Section 106 agreements to reflect impact of housing provision on local schools and match funding the DfES Seed Challenge grant and give priority to school bids which are aimed at improving standards.

Further actions and targets to achieve this improvement priority include completing major building projects to improve accommodation in primary, secondary and special schools and developing Extended Schools, resulting in more effective use of schools sites and buildings throughout the day, especially breakfast clubs and after school activities.

.

Service plan developments that underpin this improvement priority include a joint review of primary school meals service as part of a Government initiative on health in schools and develop kiosk libraries which should result in wider participation and usage of library service aimed at pupils & adult education students and improve and modernise the provision of secondary education, by investing in school accommodation.

6.2.5 Improving the life chances for disadvantaged teenagers, through improvements to their education, training and support

By 2007 we aim to ensure that no teenagers are without employment, education or training placement after the end of compulsory schooling. We also aim to increase school attendance rates, increase the numbers of children supported within schools without the need for a statement of special educational need, reduce the numbers of pupils leaving schools with no qualification and increase the performance at GCSE of pupils being looked after by the Local Authority.

Initiatives already underway include improving management and provision for Key Stage 3 & 4 pupils at the pupil referral unit, achieving the LEA's PSA target for raising secondary school attendance, a review of child protection practice and procedures within education and putting in place a strategy for future special school provision.

Further actions we will take to achieve this improvement priority include developing systems for monitoring the effectiveness of provision thereby improving performance management, improving information sharing on identified vulnerable individuals and raising the profile of vulnerable children.

Service plan developments that underpin this improvement priority are to extend the project with the Bath Foyer, Twerton working with disadvantaged young people (16-24s), using Museums to engage with hard to reach groups, sustaining improvements in practice resulting from implementation of the Climbie Audit Improvement Plan and establishing a "Sport Forum" to facilitate joined up working with other groups active in this area to help deliver social & health benefits.

6.2.6 Improving the Quality of Public Transport, Roads and Pavements and Easing Congestion

The current levels of funding for Transportation will not make a discernable difference to the quality of roads, pavements or the development of real alternatives to improve access and tackle congestion. This situation has developed incrementally over many years and comprehensive solutions cannot be delivered in the short term.

Recognising this situation, by 2007 we will have in place a medium term, resourced plan to recover the maintenance backlog. The Council will also have completed a 20 year Vision for Transport which will identify local and sub-regional projects to deliver real alternatives that improve access and we will have started implementing the first five years of the plan.

Initiatives already underway to achieve this improvement priority include the procurement of a Strategic Transport Partner to work across all areas of transportation, bringing new approaches and perspectives, the implementation and monitoring of pilot community transport initiatives and the identification of Section 106 (Planning Conditions), where justified to improve the traffic network infrastructure.

Further actions we plan to take to achieve this improvement priority include procuring a Commercial Partner to develop over 20 years the Park and Ride Service and a Rapid Transit principal network and have completed a fundamental review of existing transportation revenue expenditure, including carrying out an analysis exercise to highlight needs for additional revenue that will deliver required outcomes.

Service plan developments that underpin this improvement priority include pursuing opportunities to utilise council vehicles on public service routes and increasing investment in public transport provision, bus subsidy & concessionary fares investment. Traffic congestion will be reduced by improving road safety, reducing the effects of traffic bottlenecks and looking at suitable longer term alternatives.

6.2.7 Reducing landfill

By 2007 we aim to have reduced waste to landfill from current 58,000 tonnes to 52,000 tonnes per annum by a combination of domestic waste reduction and recycling measures as part of the Council's Zero Waste Strategy.

Initiatives already underway include the development of an Environment Park, a new Waste Strategy incorporating Zero Waste and comprehensive door-to-door recycling collections.

Further actions we will take to achieve this improvement priority include a phased review of domestic waste collection regimes (methods and frequency), detailed planning and development for the transformation of Civic Amenity Sites to Recycling Centres and investment in continuing door to door collections for plastics, cardboard and composting to mitigate future Landfill Tax increases.

Service plan developments that underpin this improvement priority include recycling leaves from road sweepings, a campaign to extend consumer understanding of recycling issues and opportunities through the Change 21 Partnership and ensuring relevant partners are involved in the Community Strategy BE GREEN key partnership, which will engender a culture of responsibility for waste and recycling and various initiatives to reduce landfill.

6.2.8 Improving the urban public realm (`liveability')

By 2007 we aim to improve, in a tangible way, the quality of urban public realm in a considered, coherent and planned manner. In the first instance through targeted transformations of spaces and initiatives focussed on street scene improvements.

Initiatives already underway include development of a Public Realm Policy, new city centre governance arrangements to tackle cross-cutting issues such as a delivery regime for commercial vehicles, access and traffic flows in and around the core city centre and the development of the Western Riverside master plan and design policies.

Further actions we will take to achieve this improvement priority include encouraging Housing partners to focus on improvement of the public realm in the management of their estates, developing a coherent advertising regime in Bath city centre and investing in improvement projects that transform areas. The Council's objectives in improving the quality of the urban public realm in the Bath and North East Somerset area will be developed having regard to improving the social, economic and environmental value in areas, whether they are urban or rural.

Service plan developments that underpin this improvement priority include development of parks & green spaces through a strategic review of Open Space management, improved environment through provision and management of street furniture, improved footways and ensuring a co-ordinated approach to delivery improvements to the urban public realm.

6.2.9 Improve Customer Satisfaction

By 2007 we aim to improve customer satisfaction through a number of initiatives such as integrated access channels to services (kiosks, service access shops, contact centre, mobile workers, web), which will mean customers are dealt with at their first point of contact with the Council. Information and services will be integrated, holistic and delivered with, by or for partners.

Initiatives already underway include a Customer Access Programme to co-ordinate and deliver projects such as kiosks on street, an HR improvement strategy which will deliver flexibility, skills and introduce workforce planning to make this possible, co-location of libraries with other services and increasing services available to customers electronically.

Further actions we will take to achieve this improvement priority include the delivery of an IT infrastructure that supports initiatives such as better telephone services, on line payments and on line booking facilities (both public facing and internal), paper archives changed to paperless via scanning and digitisation and an accommodation strategy which will reduce current reception areas and provide spaces for service access shops and a call centre.

Service plan initiatives which underpin this priority include developing single assessment processes for people needing care and/or housing services and integrating our services with those of other agencies. The Community Warden scheme will be developed to increase the range of queries and requests that can be dealt with on the spot. Generally we will improve the range of information available to our customers, and make it easier to access that information. The internet will be used to increase the numbers of services and facilities that can be accessed on-line from home PCs, on-street kiosks and/or PCs in Libraries and other public buildings. We will be implementing the Community Strategy and effective partnership working, encouraging partnerships to work together to promote the "liveability" agenda, including tackling litter, graffiti and anti-social behaviour.

6.2.10 Develop a sustainable economy for Bath and North East Somerset

(Previously Deliver improvements through project working)

The Council wishes to develop partnerships and drive projects to generate a sustainable economy with a more balanced mix of employment, in line with the Sustainable Economic Development Plan `Towards 2013'. Pursuing this as an improvement priority will have a significant impact on the full range of improvement priorities such as improving urban public realm, increasing affordable housing and improving traffic congestion. To pursue this long-term goal, the Council will provide the leadership and drive on a selected number of key development sites.

Towards 2013 contains actions to ensure a better balance and a reasonable span of employment opportunities across a variety of different business sectors, adequate access for the workforce needed to sustain this range of business and employment opportunities, and affordable housing for the future. This will make the area less reliant on its current income streams derived from the service and retail sectors and will ensure that Bath and North East Somerset has the flexibility to sustain impacts that could otherwise have an adverse effect, such as changes arising from world events or economic downturn. The strategy will be implemented in partnership with key organisations and businesses.

Developments need to be prioritised and managed carefully. The Council's objectives in regards to this priority are to facilitate and enable projects which will contribute to building a sustainable economy. Examples of how the Council will do this include partnering with good development partner(s), making investment as appropriate, supporting infrastructure development, ensuring that all developments the Council is involved with support the achievement of the Council's objectives and ensuring effective scrutiny of the management of major projects.

Within the period to 2007 the Council will focus its energy on the Western Riverside development which is key to achieving the objectives above.

An action plan to deliver this improvement priority will be developed with stakeholders and partners by the end of April 2004.

7 STRATEGIES FOR CREATING FINANCIAL AND ORGANISATIONAL HEADROOM AND CAPACITY

The resources (e.g. money, time) needed to achieve the outcomes of the Improvement Priorities will not materialise by themselves. Through the Corporate Plan strategies have therefore been devised to create the financial and organisational headroom and capacity needed to ensure that resources can be directed towards its priorities. These strategies involve:

· the release of funding as a result of improved productivity or income generation (service standards should remain broadly the same, but costs will be reduced)

· creating greater organisational flexibility (quicker response, adaptability to change, "can-do" culture etc)

· the introduction of sustainability practices as one of the means by which the Council can achieve organisational shift and headroom, increasing capacity through the more efficient use of resources.

Successfully achieving these strategies will create headroom and capacity without significant reductions in service levels. Given the timescales available to develop and implement these strategies and the need to target resources most effectively, it should be recognised that it will also be necessary to consider the redirection of funding from other services, which may involve the diminution of service scope or standards.

In pursuing these strategies, the Council will employ a number of tools.

· Continue the programme of "improvement projects" to identify and prioritise productivity and organisational improvements within and across services. The Council Executive will review and amend the existing programme in the light of this Corporate Plan.

· Complement improvement projects with a series of expenditure reviews on selected services, using a variety of techniques such as activity based costing, to highlight areas of possible productivity gain and cost reduction. Consideration is currently being given to the methodology and resources to be applied to this work and once this is complete, the Council Executive will agree a programme of reviews and targets.

· The Business Improvement Service (BIS), provided by the Council's partner HBS Business Services Group, is intended to act as a catalyst for continuous improvement within the Council, working with services to identify business improvement opportunities and developing those ideas into robust and deliverable projects. The Council Executive will consider the proposed BIS Programme for 2004/05 at its April meeting.

The Council has for some time had targets of continuous improvement across all services and has negotiated a Public Service Agreement with central government that requires an overall improvement in cost-effectiveness. For the period to 2007 there are some key projects which are central to achieving greater cross-Council productivity as follows.

B7 Through the long-term office accommodation project the Council will work to get better value from its investment in office accommodation and internet technology by introducing some shared use of office space (via hot-desking), reducing the number of different office locations for archives by moving to electronic records where possible and introducing further flexible working initiatives. The Council Executive is due to agree its preferred location for a new office building at its February meeting, and commit to progressing the project with urgency.

B7 By implementing the agreed HR Strategy action plan, the Council will identify and make the changes needed to its workforce to deliver Council priorities and will develop increased flexibility in the deployment of staff and ways of working with partner organisations. The Council will use retraining and redeployment to reduce overall ancillary staffing costs of changing priorities.

B7 The Council will co-ordinate its work to attract external funding and maximise the impact of resources put into bidding processes, including those with partners. It will continue to 93invest to save94 in order to achieve sustainability for future years.

B7 Opportunities to reduce overhead costs will be explored through new approaches to procurement, sharing specialist resources between agencies and eliminating internal duplication of effort.

B7 New opportunities offered by the Local Government Act will be explored, for example the discretionary charging power. The option to remove existing Council Tax discounts on second homes has already been agreed by Council and will be implemented from April 2004.

All of the above require changes to organisational culture. The Council will invest in management and staff to develop the culture needed to manage change well and to deliver continuous improvements to efficiency and effectiveness. Current custom and practice in the way the Council works will be scrutinised to identify areas where new ways of doing things can free up staff resources without loss of service.

In addition to the above cross-Council initiatives, all Services will investigate ways to improve productivity. The Council's Service Planning process enables Services to focus on the changes needed to deliver the Council's Improvement Priorities within its financial constraints. It provides the means for Service Managers to work through with elected Members the detailed implications for services, including implications on resources - workforce, technology and property. Some specific examples detailed in service plans include:

B7 removing surplus spaces in schools, thereby releasing funds currently locked into fixed costs and potentially freeing up land for sale or alternative use.

B7 implementing new technology systems in Planning, to improve customer access to information, streamline the administration associated with planning applications, improve turnaround time and free up expensive storage space.

B7 the recent replacement of the financial management system and the current upgrade of personnel and payroll systems provide the opportunity for better management information and a significant reduction of manual input and re-keying of data.

In some services, the need to redirect resources may mean that previous levels of service cannot be maintained. The Council can not afford to do everything to the highest standard. The implications of any changes will be properly analysed through the Service Planning process prior to implementation of these projects. Service Plans for 2004/05 are available in an advanced draft form, and are available as background papers to this Corporate Plan. Following approval to this Plan and the Budget for 2004/05, Service Plans will be finalised and subject to approval by Executive Members via the Weekly Decision List in March/April 2004.

7.1 Organisational Improvement Actions

The Council aims to increase public awareness of and confidence in the Council and its various roles: Community Leadership, representation, policy development, decision-making, scrutiny and regulation. In order to achieve this, actions focusing on the development of the Council's organisational processes include:

B7 improved consultation with the public and market research to support strategic and operational decisions

B7 improved access to information, communications and training and development for councillors to improve councillors' performance, motivation and satisfaction

B7 developing an enhanced Community Leadership role for the Council as well as improved strategic planning and operational co-ordination. There will also be improved partnership working through the development of key partnerships for transport and culture, and the streamlining of existing partnerships.

B7 through the implementation of the HR strategy, use of workforce planning and management development to extend the skill base and adaptability of the workforce at all levels to meet corporate priorities effectively

B7 information technology will be optimised to improve services

B7 continue to develop our risk management and project management processes across the organisation

7.2 Risks and Constraints

The Council does not operate in isolation - neither is everything certain to go according to plan and it is important to recognise from the outset the risks and constraints upon this Plan. Each year the Council carries out risk assessments to identify key risks facing the Council and the actions needed to manage those risks.

The most recent risk assessment highlighted the following top three risks:

· service cost escalation undermining prioritisation

· exposure to financial liabilities arising from risks on major development projects

· Government demands competing with local initiatives resulting in capacity overload and on occasion failure to deliver.

To manage these risks a number of mitigation actions and strategies have been implemented as follows.

B7 Option appraisal, project and risk management

B7 Effective and integrated corporate, service and financial planning

In budgetary terms, the Council protects itself against risk through the holding of balances and reserves. The current target, based on risk assessment, is to hold around A37M revenue reserves plus A35M capital in reserves and high liquidity assets. As actual levels are below the target level, it is necessary to continue to build up balances and reserves over the period of the Corporate Plan.

7.3 Financial Strategy and Financial Plan

The Corporate Plan Framework Document put forward a financial strategy in order to focus resources on the Improvement Priorities, alongside a target to set annual Council Tax rises in line with the government guideline. The main points of the financial strategy required over the period 2003 - 2007 to achieve these aims were as follows.

· Financial headroom will be allocated towards the Improvement Priorities and linked to achievement of specific results

· For all services provided by the Council, clear financial planning targets will be set. Service Plans will link performance targets to required levels of resources, identifying the requisite workforce planning, IT and accommodation needs

· Financial targets for education and social services will, over time, reflect a tempering of the rate of growth so that the gap between spending and the government's norm (FSS) is narrowed; this will enable local income to be seen to assist local priorities

· In order to create financial headroom, revenue funding will be released within the organisation through greater productivity and some revenue funding will be redirected from other services resulting in more revenue flexibility being achieved by 2005

· Capital expenditure will be used, only where thoroughly justified, to help fund Improvement Priorities and to invest in productivity improvements which create future years' revenue headroom. Asset-holding will be reviewed in order to ensure best use of resources whilst borrowing is likely to be the principal source of finance for additional capital spending in the short- to medium-term

· Capital expenditure will also be used, again only where thoroughly justified, on a commercial basis, to increase investment to assist the sustainability of the Council's key income streams - notably its commercial estate, museums and car parks

· Recognising that it has very limited funds, the Council will actively seek external funding, especially for schemes that fit Improvement Priorities

B7 Recognising inherent financial risks, the Council will continue to build balances over time to a level which matches its risk assessment (see Risks and constraints in section 7.2 above). Active management of budgets will continue to ensure financial control thereby avoiding budget pressures and overspending from subverting the overall Corporate Plan.

Following the approval of the Corporate Plan Framework Document, a Financial Plan for the period 2004/05 - 2006/07 has been devised, based on the above financial strategy.

As a crucial element of the strategy is to create financial headroom - funds which can then be invested to pursue the Improvement Priorities - a framework of revenue financial planning targets has been set in order to generate headroom over the 3-year period. Once achieved, headroom can be allocated (likely to be in years 2 and 3 of this Plan) towards costed proposals which emerge through the service planning process and which demonstrate a significant contribution towards achieving the Improvement Priorities. This framework links finance and performance and service standard targets and is shown in the following table.

Revenue Target

Performance / Service Standards Target

Indicative % change over 3 years

Increase

Improvement

+2%

Slight Increase

Improvement

+1%

No change

Improvement

0%

Tempering of growth

No change, achieved by productivity gain

- 3% to -5% (compared to FSS increases)

Reduction

No change, achieved by productivity gain

-3%

Larger reduction

May involve some lowering of standards in lower priority services

-5%

The application of Services to this framework is shown in Annexe 2 to Appendix 2. The application and the percentage changes will be reviewed annually in the light of changing circumstances.

The current draft financial plan incorporates the above revenue targets and can be summarised as follows:

 

2004/05

A3M

2005/06

A3M

2006/07

A3M

2003/04 Revenue Budget (adjusted for Fire, Environment Agency and Benefits transfers)

149.7

149.7

149.7

Add Inflation and other Financial Plan changes

+12.6

+23.4

+32.0

Less Headroom created by Financial Planning Targets & unspecified additional savings

-1.8

-3.7

-5.5

Equals Projected Revenue Budget

160.5

169.4

176.2

Compare with Revenue Budget consistent with assumed Council Tax rise

160.7

170.45

178.85

Equals Headroom (or Shortfall) for Reinvestment (or Reduction) year on year movement

+0.25

+0.8

+1.6

Further detail on the proposed Financial Plan is shown in Appendix 2.

It should be noted that no allowance has yet been made within the Plan for the likely increase in employers' pension's contributions in 2005/06. This is a national issue and will affect all local authorities, with a potential impact of up to A33M. Given that there is considerable uncertainty regarding the precise financial impact of the revaluation and any extra funding from Government, it has been excluded. However, Members should be aware that it may impact either on headroom or on Council Tax. Further information will not be available until autumn 2004.

The table shows that if the Financial Plan targets are achieved, then there is sizeable financial headroom in 2005/06 and 2006/07 (A3800k and A31.6M respectively) but little in 2004/05, when the targets mainly achieve containment rather than headroom. In 2005/06 and 2006/07, therefore, there will be the opportunity to use headroom for investment in Improvement Priorities. Potential schemes will be developed during 2004/05 for consideration and approvals, as part of the annual Corporate Plan review and update process. It should also be noted that the Council is committed to finding more headroom than has been identified so far in order to fund improvements.

This however can only be the case if financial plan targets are fully achieved and all new pressures are contained. There is no contingency provided for 2005/06 and 2006/07 so any extra cost pressures and/or unachieved financial plan targets will eat directly into the projected headroom figures. Some 93leakage94 is therefore inevitable and extra effort will be needed to create additional headroom.

On capital, the Financial Plan is based upon:

B7 the relevant service Government capital guidelines (applies to Education, Housing and Transport) as in previous years

B7 additional earmarked Government and other 3rd party capital grants and borrowing permissions

B7 existing financial plan allocations, subject to review.

In addition the draft financial plan assumes that around an additional A35M will be raised each year as unsupported borrowing under the new Prudential Code arrangements. As a broad planning guideline, it is intended that the A35M is allocated as follows.

B7 To assist in achieving the Improvement Priorities (cA32.5M pa)

B7 To create headroom through productivity improvement, notably through the Business Improvement Partnership with HBS but also possibly through other invest-to-save mechanisms (up to A31M pa)

B7 To assist the sustainability of the Council's key income streams (up to A31M pa)

B7 To assist the progress of the Council's major projects (around A30.5M pa)

B7 To provide sufficient contingency and protection against risk (min A30.5M pa)

Annexe 1 to Appendix 2 provides further indicative allocations within the 93improvement priority94 block above, showing minimum and maximum indicative allocations. These will be reviewed annually and allocations made within the Budget and Service Planning processes. In considering allocations, it will be important to weigh up the relative impact and value for money of spending on each of the key priorities. There are major capital spending needs on affordable housing, schools, transport as well as on major projects and other improvement priorities, and it is not possible to meet all needs fully. In achieving a balanced programme, the Plan does indicate a continuation, beyond 2004/05, of the level of annual investment in affordable housing currently being financed from the 1999 stock transfer receipt, at around A33M pa (total housing programme cA34M pa).

In providing the A35M unsupported borrowing, it is stressed that borrowing should not be seen as an easy option and it is required that:

B7 all proposals will be subject to rigorous justification and quantification of targets for outcomes (whether financial, performance or service outcomes). It is expected that the justification will take the form of a detailed business case

B7 all agreed schemes will need clear project plans, timescales and monitoring arrangements prior to commencement

B7 any invest-to-save allocations will result in automatic adjustments to the relevant revenue budgets. Invest-to-save schemes will need to demonstrate rates of return significantly in excess of the cost of borrowing (i.e. hurdle rates) in order to provide protection against risk. The current cost of borrowing within the overall Financial Plan is 9.5% pa (4% principal repayment and 5.5% interest);

B7 asset holding should be reviewed and challenged proactively to provide future capital receipts and minimise the need for Council borrowing, where those assets do not generate sufficient financial or service benefit.

7.4 Implementation Plan

The Corporate Plan of itself will not deliver improvement. To deliver improvement it is intended that the Plan will be developed and implemented through a series of phases. Phases 1 and 2 (which were set out in the Framework Document) are now largely complete, but development will continue, as follows.

Phase 2 (remainder) - to spring 2004

B7 Final sign-off of Service Plans. This work to include critical review of draft service plans by Executive Members, Directors and Heads of Service to ensure that plans and resources are fully aligned with the Corporate Plan - March 2004

B7 Identification of key targets for performance management arrangements

Phase 3 - Mar 04 to Feb 05

B7 Performance Management arrangements to ensure monitoring and review of Corporate Plan implemented

B7 Headroom strategies delivering initial savings

B7 Improvement Priorities being implemented - emphasis on low revenue cost quick wins and targeted capital investment

B7 Corporate Plan reviewed in light of year 1 progress

B7 Budget & Performance Indicator targets for all Improvement Priorities 2005/06 set

B7 Service planning further developed

Phase 4 - Mar 05 to May 07

B7 Headroom strategies delivering more savings, enabling revenue reinvestment

B7 Improvement Strategies developed to completion - revenue investment as well as capital

B7 Corporate Plan reviewed and updated annually in conjunction with annual Service Plans.

8 MONITORING AND REVIEW OF THE CORPORATE PLAN

8.1 Key performance indicators

Key Performance Indicators (KPIs) will be used to ensure that any deviation from our plans to implement improvement priorities is highlighted so that prompt corrective action can be taken. KPIs will supplement existing performance measurements so that priorities for action can be set. Our existing performance management framework has been recognised by external inspectors as an excellent system, and we intend to maintain this strength.

KPIs have been in development since June 2003, when an initial set was selected by Directors in response to requests from Overview and Scrutiny panels. They will be developed by a combined Executive member and Officer Steering Group to ensure they reflect Council priorities as they change over time.

Other Performance indicators will continue to be monitored to ensure "business as usual" responds to community needs.

8.2 Key targets for services

The detail of how these targets will be achieved is contained in service specific plans. The targets shown here are in addition to those set out in the rest of this plan.

Transport

B7 2* rating achieved and maintained with improving efficiency

B7 Planned improvement in PI's achieved

B7 Improved Community Satisfaction (relative to other Councils) to 2nd quartile

Social Services

B7 Maintenance of 2* rating for overall service with improved efficiency

B7 Main area for improvement is Adult Services

Housing

B7 Achievement and maintenance of 2* rating for overall service with improved efficiency

Education

B7 Maintenance of 2* standard for overall service with improved efficiency

B7 Improvement in numbers continuing in Education/Training post 16

B7 Exclusion rates reduced

B7 Improvement in Post 16 education

B7 Improvement in fabric of school buildings

B7 Public Service Agreement targets delivered

Community safety

B7 Proposals for joint service/police working to address day-to-day community concerns

B7 Relative to other Councils, an improvement in the communities' perception of their safety.

9

LIST OF APPENDICES

Appendix 1 - Improvement Priority Plans

Appendix 2 - Financial Plan commentary

B7 Annexe 1 - Capital Planning 2005/06 & 2006/07

B7 Annexe 2 - Revised Financial Planning Targets

APPENDIX 1 - IMPROVEMENT PRIORITY PLANS

IMPROVEMENT PRIORITY

INCREASE AVAILABILITY OF AFFORDABLE HOUSING

Brief description of improvement to be achieved by 2007

An overall increase in the amount and range of affordable is a long term goal (10-20years) requiring some large and far reaching decisions e.g. in relation to spatial planning, housing density and resource allocation. By 2007 we will have established and be working on an affordable housing strategy that will be complemented by an agreed local plan, which will enable us to identify proactively suitable residential sites and work with a range of partners to develop a variety of housing tenures. It is envisaged that in the lifetime of this corporate plan actions undertaken will seek to minimise the growing gap between affordable housing and demand/need.

Initiatives already underway to achieve this improvement priority

B7 Local plan development - with associated policies

B7 EPH development will produce new housing units for older people

B7 Western Riverside - 30% minimum affordable housing

B7 Work with Bath University & Bath Spa University College to manage student housing needs

B7 Sub regional Housing market study underway

B7 Lettings and Choice pilot

B7 LSP - key worker housing, bidding for additional funds at regional level, work on protected short term tenancies for key workers

B7 Complete 6 year investment strategy to build 600 new homes by the end of 2005

Further actions we plan to take to achieve this improvement priority

The Council is developing an affordable housing strategy recognising that a number of areas need to be brought together to optimise the potential for affordable housing in the area. This will include working with the universities to manage student housing need and lessen the impact on available affordable housing for local residents:

B7 optimising the use through the planning system of contribution to affordable housing from developers

B7 ensuring that it is a key feature within the local plan development

B7 manage the development of additional extra-care affordable housing as part of provision of three Community Resource Centres for older people, to achieve an increase in affordable housing options for older people

working sub-regionally with neighbouring authorities to look at optimising potential for affordable housing across the area and considering the transport needs of such developments; together with partners the Council will develop key worker schemes to support the housing of lower paid public service workers in the area

Service plan developments that underpin this improvement priority

B7 Encourage public service employers to develop innovative approaches to meeting the current & future housing needs of their staff

B7 Development of a Corporate Property Strategy

B7 Adoption of the Affordable Housing Strategy

B7 Reducing the use of B&B accommodation

B7 Use of void & vacant properties to house homeless residents

B7 Promote Bath & North East Somerset as an area where high quality teachers wish to work & develop the effective implementation of the workforce reform

B7 Student Housing Policy - minimise the negative effect of houses in multiple occupation on the affordable housing market and neighbourhoods

B7 Development of framework for instigating and co-ordinating physical development and improvement across Radstock Town Centre.

B7 Development of framework for instigating and co-ordinating physical development and improvement across Keynsham Town Centre.

B7 Development of framework for instigating and co-ordinating physical development and improvement across Midsomer Norton Town Centre.

B7 Bath City Centre Governance and Framework for Action

Financial Plan information in regards to this Improvement Priority

Planned capital investment in affordable housing c A39m over the period 2004-2007.

Funding through grant of work to provide better alternatives to bed and breakfast accommodation A325k

IMPROVEMENT PRIORITY

PROMOTING THE INDEPENDENCE OF OLDER PEOPLE

Brief description of improvement to be achieved by 2007

We are aiming jointly with the Primary Care Trust and other NHS Providers to deliver services in an integrated and timely way that will promote, retain or restore the maximum level of independence possible for individuals, with the least intervention necessary (i.e. the right service, in the right place, at the right time).

Initiatives already underway to achieve this improvement priority

B7 Improving the speed of response in assessing the needs of and providing services to more vulnerable older people

B7 Joint working with the Primary Care Trust - 93Whole system94 approach to older peoples care

B7 Develop Community Resource Centres offering a wide spectrum of care and roll out 93in reach94 nursing to the independent sector

B7 Home care service review to provide a more rehabilitative and flexible service

B7 Joint working with Benefits Agency to improve the take-up of benefits

Further actions we plan to take to achieve this improvement priority

The Council will take measures to ensure that older people can access services more swiftly and to improve its speed of response to referrals through the enhancement of its duty service, by improving the delivery of community equipment, by reconfiguring its home care service to assist people regain or maintain daily living skills and through improving its external and internal information infrastructure.

The Council will progress its development of three centres of excellence in each of the main urban areas of Bath & North East Somerset. The centres will provide a range of living opportunities with varying degrees of support available according to individual need. In addition through close working with the Primary Care Trust a range of health and social care facilities will be made available on or from these sites.

We will also ensure that transport developments (see action plan on Traffic, Congestion, Public Transport and Roads and Pavements) address the needs of older people.

Service Plan key developments that underpin this Improvement Priority

B7 Work with a wide range of partners to maximise take-up of benefits & tax pension credits

B7 Reduce the number of delayed discharges from acute beds attributable to Social Services through increased care assessment capacity & increased provision of intermediate care through re-enablement service

B7 Re-modelling of the in-house home care service to become more flexible & more intensive

B7 Single assessment process for older people is to be developed for older people requiring care services, and home care and day services are to be developed to help people remain in their own homes

B7 Improving services for older people with mental health problems

B7 Increase the number of people in all client groups receiving a direct payment in lieu if services

B7 Progress the re-provisioning of older persons' housing & care

Financial Plan information in regards to this Improvement Priority

Council investment of A36m in the provision of 3 Community Resource Centres (total cost A315m including contributions from partners).

Grant funded expenditure of A353k for the PSA scheme to improve the quality of life and independence for older people.

Increased funding of home care.

IMPROVEMENT PRIORITY

REDUCING THE FEAR OF CRIME

Brief description of improvement to be achieved by 2007

Working closely with our partners in the Community Safety Partnership such as the Police, we aim by 2007 to increase public confidence and see a reduction in the fear of crime. This will be achieved by the Partnership improving and maintaining the public environment or `street scene', reducing the level of vehicle crime and burglaries and by working positively in a preventative way with young people to avoid their involvement in youth crime and disorder.

Initiatives already underway to achieve this improvement priority

B7 Community Safety Partnership - 6 priorities -persistent offenders, youth crime, drug misuse, victim support, reducing fear of crime and developing local action

B7 Recommissioning treatment services in DAT

B7 Vehicle Crime action plan including: Safer car parks initiative, vulnerable vehicles scheme and vehicle recognition CCTV

B7 Abandoned vehicles scheme and Graffiti removal service

B7 Community wardens scheme (currently reviewing these together with police schemes)

B7 Police teams moved into to the Hollies at MSN - increase visibility of police

B7 Proactive communication strategy with the general public

B7 Cleansing of public realm and safe disposal of facilities for needles used in drug misuse

B7 Maintenance and prioritised expansion of street lighting

B7 Designing safety considerations into the planning process

B7 Development of Community Safety Action Groups

B7 Elder Aware Project and Bobby Van scheme

B7 Support for voluntary organisations including Victim Support and Support Against Racist Incidents

B7 The Compass project working with young people at risk of anti social behaviour

Further actions we plan to take to achieve this improvement priority

The Council will continue to work in partnership to pursue the Community Safety Partnership's six priority areas for action, which are persistent offenders, youth crime, drug misuse, victim Support, reducing fear of crime and developing local action

Many, if not all the Council services have a role to play in increasing the safety of our communities and reducing the fear of crime. It is also important that we work in partnership with other key organisations such as the Police, the business community, registered social landlords and others.

Specifically to reduce the fear of crime

B7 The council will address the 93street scene94 in a variety of ways from quick removal of graffiti, abandoned vehicles, dumped rubbish and other small but significant issues which together reduce the public's confidence in the streets and urban environment as a safe place to be.

B7 Together with the Police we will review the various warden schemes or 93extended police family94 to optimise the 93on street presence94 and improve public confidence.

B7 Additionally, we will improve access to and the amount of drug treatment programmes to try and break the link between street homelessness and drug misuse.

B7 We will work with partners to support the development of local Community Safety Action Groups to involve local people in developing solutions to the issues which concern them

B7 We will support a range of initiatives for people who may be more vulnerable to crime or fear of crime including older people, black and ethnic minority communities, disabled people, and victims of domestic violence

B7 We will develop and implement an anti social behaviour action plan to ensure a rapid response to incidents of anti social behaviour

B7 We will target work on vulnerable young people, excluded or at risk of exclusion from schools to sustain or re-engage them in education training and employment through a variety of means both in supporting schools themselves, through prevention work by the Youth Offending Team and an increasingly focused and co-ordinated approach by the youth services.

Service plan developments that underpin this improvement priority

B7 Further develop the community warden scheme & identify potential for further integration with other service areas

B7 Draw up management plan for Abbey Churchyard in partnership with local stakeholders

B7 Development of a Local Preventative Strategy including the development of Information Sharing (Identification Referral & Tracking)

B7 Provide security presence at Parade Gardens

B7 Action Line - amendment to base budget

B7 Provide additional funding for graffiti removal

B7 A cleaner environment through review of street cleansing

B7 Make inclusion achievable by building the trust, confidence & capacity of schools & the authority to meet the needs of children & young people

B7 Licensing Act 2003: Council responsibility aimed to:

B7 Prevent crime & disorder,

B7 Safe guard public safety

B7 Prevent nuisance

B7 Protect children from harm

B7 Street Lighting improvement

B7 Improve the quality standards for youth, adult & community education service delivery

B7 Improvements to local environment quality

B7 Ensure there is a strong focus on the LSP's work on joint working to promote liveability in local neighbourhoods, & that there are close links with community safety issues

B7 Town Ranger Centre Scheme for Norton Radstock (Joint proposal with Sustainability & Economic Development Services and Commercial Services) - pro-active presence to ensure that street scene issues are dealt with quickly, effectively and in co-operation with local stakeholders such as Town Council, Police and Chamber of Commerce

B7 Enforcement of Litter Fines It is intended to introduce the powers with the maximum possible publicity and the emphasis on prevention rather than the issuing of fines

B7 Improve and increase creative extended education and lifelong learning opportunities

Financial Plan information in regards to this Improvement Priority

Investment in reducing of vehicle crime A3150k over the plan period.

Community safety and drug action team funding sustained over the planning period.

IMPROVEMENT PRIORITY

IMPROVING THE ENVIRONMENT FOR LEARNING

Brief description of improvement to be achieved by 2007

By 2007 we aim to have secured additional capital to invest in improving the quality of learning in classrooms and schools. This, together with more effective management of capital resources, will also enable us to meet our Asset Management Plan targets and ensure sufficient resources to successfully implement changes arising from area reviews.

Initiatives already underway to achieve this improvement priority

B7 Joining up funding streams wherever possible to maximise the scope of works. This includes securing significant contributions from schools from their devolved capital to expand projects to meet LEA and school priorities

B7 Securing maximum capital available through Government initiatives whenever possible. Recent successes include Targeted Capital Grant and Teaching Environments for the Future

B7 Securing developer contributions through Section 106 agreements to reflect impact of housing provision on local schools

B7 Achieve capital receipts for reinvestment in the school building stock through disposal of surplus school land and property wherever possible.

B7 Match fund the DfES Seed Challenge grant and give priority to school bids which are aimed at improving standards

Building Schools for the Future (BSF) is a new Government initiative which is aimed at a re-generation of the nations secondary schools over 10 -15 years. It is referred to as a `once in a generation opportunity' and will see a doubling of existing schools capital from 2005-06. All LEAs are invited to bid but priority initially will be given to LEAs with poorest standards and levels of deprivation. Successful LEAs are likely to receive A3100 -A3150m based on groups of secondary schools. B&NES will not be in the first wave but should aim to be in the second group of LEAs. Bids must reflect the LEA's strategic plan for secondary organisation to which all stakeholders must be signed up. Expressions of interest must be submitted by Dec 2003. Announcement in March 2004.

Further actions we plan to take to achieve this improvement priority

The focus on standards and deprivation may make it difficult for this LEA to succeed with an early BSF bid. Should this not be successful serious consideration could be given to developing a PFI which is likely to be the only other way of securing such significant amounts of capital. Experience shows that for small LEA's the costs of developing a PFI bid is significant. However this may be a worthwhile investment in order to achieve the step change needed and which the Council from its own funds is never likely to achieve. A PFI bid must be based on a clear, strategic view of future needs; authorities who have had to close PFI schools have run into significant difficulties.

B7 Complete major building projects to improve accommodation in primary, secondary and special schools

B7 Complete reviews of 12 primary school planning areas (NB Radstock area already undertaken as part of Radstock Renaissance)

B7 Development of Extended Schools

B7 Submit bid for funding under Building Schools for the Future initiative

B7 Undertake initial consultation exercise with key stakeholders regarding secondary school provision in the Greater Bath Consortium

B7 Join up funding streams to secure maximum benefit from capital investment in schools

Service plan developments that underpin this improvement priority

B7 Joint review of Primary school meals service

B7 Spend additional capital in line with the Secondary School Investment Plan

B7 Develop a corporate property strategy

B7 93Library link" Kiosk libraries - pilot in Writhlington secondary school & Peasedown St John Community Centre

B7 Improve the quality of provision by reducing surplus places in primary schools through collaboration, federation, and closure where necessary

B7 Improve & modernise the provision of secondary education, by investing in school accommodation, improving quality & opportunity at 16+, & in the longer term, the pattern of secondary education in Greater Bath.

Financial Plan information in regards to this Improvement Priority

Major investment over the plan period in schools, through government allocations (Radstock, Bath Special schools, general modernisation) plus an indicative A32m+ Council allocations, notably for area reviews.

IMPROVEMENT PRIORITY

IMPROVING THE LIFE CHANCES FOR DISADVANTAGED TEENAGERS, THROUGH IMPROVEMENTS TO THEIR EDUCATION, TRAINING AND SUPPORT

Brief description of improvement to be achieved by 2007

By 2007 we will ensure that no teenagers are without employment, education or training placement after the end of compulsory schooling. We also aim to increase school attendance rates, increase the numbers of children supported within schools without the need for a statement of special educational need, reduce the numbers of pupils leaving schools with no qualification and increase the performance at GCSE of pupils in care.

Initiatives already underway to achieve this improvement priority

· Improving Management and Provision for KS3 & 4 pupils at the pupil referral unit

· PSA target for raising secondary school attendance

· Strategy for education of looked after children

· Developing inclusion strategy specifically to include BESD

· Mainstream Additional Funding - delegation

· KS3 behaviour and attendance strategy

· Locality based support for schools (LBSS) in Education

· Review of child protection practice and procedures within education

· Development of Information Sharing and joint working to integrate inclusion and school improvement

· Widening learning / and developing thinking skills with disaffected pupils

· Creative education for disaffected pupils

· Strategy for future special school provision

· Facilitating the sharing of schools' inclusive practice and networking

· RAMP project supporting KS3 & 4 at risk of exclusion.

Further actions we plan to take to achieve this improvement priority

1. Developing systems for monitoring the effectiveness of provision / improving performance management · and the use of IT to support this (information sharing)

2. Raise the profile of vulnerable children and set a clear corporate priority for developing Inclusion.

3. Targeting resourcing to support the Inclusion agenda in particular for children with Behaviour, Emotional & Social Difficulties (BESD).

· Extend existing PRU provision to meet the needs of a wider range of vulnerable children - focussing on respite and reintegration support to pupils & schools.

· Raise the standards of education provision for pupils who are excluded / at risk of exclusion.

· Support schools in managing difficult pupils.

4. Increase in collaborative, cross agency working to develop effective multi agency services for vulnerable children.

5. No children without employment, education or training placement after the end of compulsory schooling.

Service plan developments that underpin this improvement priority

B7 Extend the project with the Bath Foyer, Twerton, working with disadvantaged young people (16-24s)

B7 Improve the health, educational attainment, training, employment & accommodation options for care leavers

B7 Sustain improvements in practice resulting from implementation of the Climbie Audit Improvement Plan

B7 Implement changes proposed by Green paper, Every Child Matters & subsequent legislation

B7 Development of a Local Preventative Strategy including the development of Information Sharing (Identification Referral & Tracking)

B7 Launch new 93Plan for Sport & Physical Activity94

B7 Establish a 93Sport Forum 93 for B&NES

B7 Kiosk libraries - pilot in Writhlington secondary school & Peasedown St John Community Centre

B7 Improve the outcomes for vulnerable pupils

B7 Make inclusion achievable by building the trust, confidence & capacity of schools & the authority to meet the needs pf children & young people

B7 Improve the quality standards for youth, adult & community education service delivery

B7 Improve and increase creative extended education and lifelong learning opportunities

B7 Teenagers into training and jobs to ensure effective referral onto work based training programmes funded by LSC

Financial Plan information in regards to this Improvement Priority

Funding through grant of measures to increase pupil attendance in secondary schools and improving the educational attainment of young people leaving care (PSA funding).

Increasing and continuing funding of detached youth workers (A335k ongoing).

IMPROVEMENT PRIORITY

TRAFFIC, CONGESTION, PUBLIC TRANSPORT AND ROADS AND PAVEMENTS

Brief description of improvement to be achieved by 2007

The current levels of funding for Transportation will not make a discernable difference to the quality of roads, pavements or the development of real alternatives to improve access and tackle congestion.

The current situation has developed incrementally over many years and comprehensive solutions cannot be delivered in the short term.

Recognising this situation, by 2007 the Council will have in place:

B7 A medium term, resourced plan to recover the maintenance backlog.

B7 A 20 year Vision for Transport which will identify local and Sub Regional Projects to deliver real alternatives that improve access and we will have started implementing the first five years of the plan.

Initiatives already underway to achieve this improvement priority

B7 Finalise the development of 20 Year Vision for Transportation.

B7 Procurement of Strategic Transport Partner to work across all areas of Transportation, bringing new approaches and perspectives.

B7 Implementation and monitoring of pilot Community Transport Initiative.

B7 Identification of Section 106 (Planning Conditions), where justified to improve traffic network infrastructure.

Further actions we plan to take to achieve this improvement priority

B7 Procure through European Advert Commercial Partner to develop over 20 years the Park and Ride Service and a Rapid Transit principal network.

B7 Detail a medium term resourced recovery plan to tackle the infrastructure maintenance backlog.

B7 Develop a detailed, costed delivery plan for the first five years of the 20 year Vision for Transport.

B7 Prepare and submit for Government Funding a fully justified `package submission' to address the traffic congestion issue for Bath (Bristol/Bath South Coast Study).

B7 Complete a fundamental review of existing Transportation revenue expenditure and analyse and prioritise needs for additional revenue that deliver required short, medium and longer term improved outcomes.

B7 Complete development and feasibility stages of key access improvement namely Park and Ride enhancements and Rapid Transit Pilot.

Service plan developments that underpin this improvement priority

B7 Pursue opportunity to utilise council vehicles on public service routes

B7 Public transport:

B7 Investment in public transport provision

B7 Bus subsidy & concessionary fares investment

B7 Infrastructure investment

B7 Investment in improving quality of information for users

B7 Resolve environmental impact of Open Top Tour Bus operation

B7 Quality Partnerships

B7 Strategic partner to develop rapid transit park & ride

B7 Highway maintenance to improve quality of public highway

B7 Improved footways

B7 Reduce traffic congestion by improved road safety, reducing the effects of traffic bottlenecks and looking at suitable longer term alternatives, possible demand management

B7 Overview And Scrutiny Review of Passenger Transport to encourage greater use of public transport and explore the opportunities for making best use of the new charging powers under the Local Government Act 2003

B7 Improve the focus and capacity of key partnerships to deliver the Community Strategy's ambitions in respect to Transport and Culture

Financial Plan information in regards to this Improvement Priority

Both grant funded work (A370k) and council capital funding (A385k) to increase bus usage (PSA).

Additional capital funding to ease congestion (part of an A319m capital programme over the plan period).

Real growth in public transport revenue funding over the plan period.


IMPROVEMENT PRIORITY

REDUCING LANDFILL

Brief description of improvement to be achieved by 2007

Reduce waste to landfill from 58,000 tonnes to 52,000 tonnes per annum by a combination of domestic waste reduction and recycling measures as part of the Council's Zero Waste Strategy.

Initiatives already underway to achieve this improvement priority

B7 Development of Environment Park with Strategic Waste Partner

B7 Development of new Waste Strategy incorporating Zero Waste

B7 Pursuing Government to pilot trial for charging of collecting non-recyclable waste.

B7 Comprehensive door-to-door recycling collections.

B7 Secure Strategic Waste Partner who aligns with Council's approach to Waste.

B7 Public Service Agreement to improve Recycling rates at Household Recycling Centres.

Further actions we plan to take to achieve this improvement priority

B7 Phase re-engineering of domestic waste collection regimes (methods and frequency).

B7 Detailed planning and development for the transformation of Civic Amenity Sites to Recycling Centres and rationalise to two through integration in the development of the Environment Park. rather than three.

B7 Invest in continuing door to door collections for plastics, cardboard and compositing to mitigate future Landfill Tax increases.

B7 Targeted promotion and awareness campaigns to support zero waste and recycling policies.

Service plan developments that underpin this improvement priority

B7 Ensure relevant partners are involved in our BE GREEN key partnership

B7 Management of refuse & recycling collections (draft proposal)

B7 Zero waste policy & implementation strategy

B7 Environment Park Development

B7 Increase types & quantities of recycling to assist minimising internal/ external rising cost trends

B7 Rationalise & improve efficiency of all domestic waste & recycling services - a project/study is being started to review the current refuse and recycling collection methodologies and frequencies which will produce recommendations for implementation in future years

B7 Bath Recycling Centre - The existing Household recycling centre at Midland Road needs to make way for the Western Riverside development project. A new site is still to be identified, although the Western Riverside Master Plan identifies a facility being located in a combined waste and transport interchange

B7 Extension of Old Welton Recycling Centre to improve household recycling facility and introduce a trade recycling centre on existing site - existing site near to capacity

B7 Campaign to extend consumer understanding of recycling issues and opportunities through the Change 21 Partnership.

B7 Business waste recycling - with Envolve to encourage business waste recycling - award scheme, extension of EMAS and Environmental Business Network

B7 Recycle Leaves From Road Sweepings - large volume of leaves is collected from roads and pavements each autumn. Landfill costs are incurred and an opportunity to re-use a worthwhile resource is lost. It is proposed to cost out the option of recycling this material with a view to changing the existing practice

Financial Plan information in regards to this Improvement Priority

Financing of the increased recycling initiatives and further costs of waste disposal - a cumulative increase of A30.9m revenue cost by the end of the plan period.

Relocation of the Bath Household Waste and Recycling Centre. This is part of the regeneration of Western Riverside area of Bath and also a proposal within the authority's Public Service Agreement.

Real growth built into planning targets for waste management services.

IMPROVEMENT PRIORITY

URBAN PUBLIC REALM

Brief description of improvement to be achieved by 2007

To improve, in a tangible way, the quality of urban public realm in a considered, coherent and planned manner. In the first instance through targeted transformations of spaces and initiatives focussed on street scene improvements.

Initiatives already underway to achieve this improvement priority

B7 Community Safety Partnership Action Plan.

B7 Development of Public Realm Policy.

B7 New City Centre Governance Arrangements to tackle cross-cutting issues.

B7 World Heritage Site Action Plan.

B7 CCTV Network Management.

B7 Targeted rationalisation of street clutter.

B7 Western Riverside Master plan and Design Policies.

Further actions we plan to take to achieve this improvement priority

B7 Encourage Housing partners to focus on improvement of the public realm in the management of their estates.

B7 Develop coherent advertising regime in City Centre.

B7 Completion of overarching Streetscape Manual as policy for Public Realm development.

B7 Devise delivery regime for 93Commercial Vehicles94 to City Centre premises.

B7 Explore 93Business Improvement District94 BID for City/Town Centres.

B7 Explore and develop new access and prioritised pedestrian proposals for City.

B7 Invest in a specific Bath based improvement project that transforms an area by improving:

B7 Social and economic vitality

B7 Street level safety and pedestrian access

B7 Attractiveness of the location to users and businesses

B7 Contributes to World Heritage Site status

B7 Visual and environmental amenity

B7 Local distinctiveness within the context of the World Heritage Site

B7 Developments will have regard to improving the social, economic and environmental value in areas, whether they are urban or rural

Service plan developments that underpin this improvement priority

B7 Further develop the community warden scheme & identify potential for further integration with other service areas

B7 Flexible business planning mechanism to allow access to capital funds through Prudential Code of Borrowing to ensure sustainability of heritage assets & their income streams in the long term

B7 Draw up management plan for Abbey Churchyard in partnership with local stakeholders

B7 Development of parks & green spaces through strategic plan

B7 Provide additional funding for graffiti removal

B7 A cleaner environment through review of street cleansing & provision & management of street furniture

B7 Improved footways

B7 Ensuring a co-ordinated approach to delivery improvements to the urban public realm

B7 Implementation of World Heritage Site Management Plan

B7 Development of framework for instigating and co-ordinating physical development and improvement across Radstock Town Centre.

B7 Development of framework for instigating and co-ordinating physical development and improvement across Keynsham Town Centre.

B7 Development of framework for instigating and co-ordinating physical development and improvement across Midsomer Norton Town Centre.

B7 Bath City Centre Governance and Framework for Action

Financial Plan information in regards to this Improvement Priority

Accelerate the programme to make Council buildings compliant with Disability Discrimination Act requirements (A31.1m)

Fund work to progress the development of Western Riverside of A32m.

Grant funding of graffiti removal A317k and capital improvements to Walcot Street and automatic public conveniences (A3116k).

IMPROVEMENT PRIORITY

INCREASE CUSTOMER SATISFACTION

Brief description of improvement to be achieved by 2007

By 2007 we aim to improve customer satisfaction through a number of initiatives such as integrated access channels to services (kiosks, service access shops, contact centre, mobile workers, web), which will mean customers are dealt with at their first point of contact with the Council. Information and services will be integrated, holistic and delivered with, by or for partners.

This will be achieved by integrating our phone and walk-in services to deal with as many public queries as possible on the spot, and providing self-service options on the web site where appropriate. Where this is not possible our customers will be referred to the correct specialist who can deal with their requirements.

Services will agree transfers of staff or resources to customer services to facilitate the 93first point of contact94 approach, which will necessitate streamlining and improving processes both at the first point of contact and in the back office. Where appropriate, services will be delivered jointly with partner organisations.

Initiatives already underway to achieve this improvement priority

B7 Customer access programme in place to co-ordinate and deliver projects

B7 InfoPlus at Midsomer Norton, The Hollies in place and delivering an initial range of services

B7 Kiosks on street have been piloted to provide access to web-based information and transactions

B7 Co-location of libraries with other services and increasing services available to customers electronically

B7 All Council Services working to get priority information and transactions available on-line

B7 Content management project to make it easier to find information on Council web site to ensure customer service improves

B7 Partnership with HBS to support Business Improvement and supply of supporting technology to provide the infrastructure and improved processes to increase customer service to provide the infrastructure and improved processes to increase customer service

B7 Implementation of the Council's HR strategy.

Further actions we plan to take to achieve this improvement priority

B7 Standard Council reception service to be developed to provide consistent customer service

B7 All libraries to deliver basic first stop shop services and be co-located with other services

B7 Telephone Services to be developed to provide consistent customer service via a Contact Centre

B7 First point of contact services access points to be provided in urban centres as part of accommodation strategy

First point of contact access points are defined as premises in our main urban areas that any member of the public can visit, to speak face to face with a member of the Council's Customer Service staff, who will provide access to the full range of the Council's services and information. The aspiration is that a majority of all queries and contacts will be dealt with at that first point of contact and not passed to other specialist or back office staff

B7 IT infrastructure e.g. Customer Relationship Management system, e-forms, Call Centre, on line payments facility, on line booking facility etc (both public facing and internal) to be developed to support first point of access to services

B7 Each service to review and change the way it provides its services so that all possible customer contacts can be delivered via co-ordinated access channels

B7 HR Improvement strategy to develop flexible skilled work force able to deal well with change needed to improve customer satisfaction.

B7 Develop partnership working so services can be jointly delivered with other agencies where appropriate.

Service plan developments that underpin this improvement priority

· A single assessment process is to be developed for older people requiring care services, and home care and day services are to be developed to help people remain in their own homes

· Integrated discharge service to be developed for people with mental health problems with improved services to support people in the community

· Integrated service for people with housing difficulties alongside development of improved options for temporary accommodation

· Introduction of cash machines to reduce time people have to wait to make payments

· Development of Community Warden Scheme to deal with more customer enquiries/ requests for action at first point of contact.

· Access to Victoria Art Gallery collection of local material via the web site

· Access to Planning applications via the web site

· Improved quality of bus information

· Improved direct provision of information about the Council and its services to the public

· Range of other improvements to quality and ways in which services are provided as set out in the detail of service plans

Financial Plan information in regards to this Improvement Priority

Capital investment of A3250,000 over the plan period, including an additional A3100,000 in 2004/05 in addition to existing ongoing revenue investment of A3330,000 a year.

APPENDIX 2 - FINANCIAL PLAN COMMENTARY

1. The draft financial plan is currently based on the following key planning assumptions:

Pay

Non-teachers - 3% p.a.

Teachers - pay increases assumed to be funded within overall increases of service.

Inflation

Generally at 2.5%, but will be varied by type of expenditure.

Interest Rates

At 5.5% throughout

Employee Pensions Contribution

This is a national issue and will affect all local authorities, with a potential impact of up to A33M. Given that there is considerable uncertainty regarding the precise financial impact of the revaluation and any extra funding from Government, it has been excluded.

SSA or FSS growth

2004/05 and 2005/06 in line with assumptions in Comprehensive Spending Review, adjusted for B&NES. Thereafter assumed a continuing similar trend in absence of national figures.

RSG or Formula Grant growth

2004/05 and 2005/06 in line with assumptions in Comprehensive Spending Review, adjusted for B&NES. Thereafter assumed a continuing similar trend in absence of national figures and assumed increase in Council Tax in settlement of 6% a year.

2. The draft financial plan produces the following key outputs:

Education

Annual real terms revenue spending to grow based on FSS cash increases, but with growth tempered to narrow the excess spending compared to FSS.

For latter years a planning assumption of between 4.7% to 4.8% growth pa has been included

Social Services

Annual real terms revenue spending to grow based on FSS cash increases, but with growth tempered to narrow the excess spending compared to FSS.

For latter years a planning assumption of 3.3% growth pa has been included (with 7.5% in 2005/06 to reflect large national FSS increases in Personal Social Services that year).

Fire

Now a separate preceptor so not included in the plan.

Other Services

Annual net revenue spending to be planned to vary service by service. This will be as a result of reprioritisation to deliver Improvement Priorities and specific spending pressures and initiatives.

Capital Financing

Revenue contributions - the Plan assumes revenue contributions to capital of A3500,000 pa.

Interest on balances and debt charges - effect of loss of interest on cash balances as result of capital programme is estimated at A31.5M in 2004/05 and (including effect of new borrowing) approx A31.6-2M pa thereafter. But FSS increase also builds in extra increase in supported capital in the plan of A30.8-A30.5m a year.

The current plan would increase working balances to around 5.8% of net spend excluding schools by 1 April 2005, assuming there are no calls on balances in 2004/05, and by about 0.7% a year thereafter, assuming there are no calls upon them in the intervening years.

There is no contingency built in for growth at present in the plan. Although it is likely that will occur from cost and service pressures which have not yet been identified, the service planning process attempts to identify these and set out the impacts of meeting plan targets. The plan does contain 93headroom94 (see below).

Overall Increase and Headroom

Net revenue spending is projected at A3160.7m in 2004/05, and increase of 7.3% on 2003/04 (adjusted figure).

For future years the base plan shows total Council spending increasing by 4.0% - 5.6% pa with no revenue deficits. Headroom of A30.8m for 2005/06 and A31.6m for 2006/07 is shown (NB subject to impact of pensions - see above)

Capital

Annual capital programmes in line with government allocations plus specific allocations for B&NES policy objectives.

The plan currently assumes an additional A35m financed from additional borrowing to finance the following areas

a) Improvement Priorities

b) Productivity Gain

c) Invest to sustain in main income streams

The attached annex provides indicative allocations for future years.

Annexe 1 - Capital Planning 2005/06 & 2006/07

Capital allocations for 2004/05 are shown in the Budget report. The Financial Plan assumes that around an additional £2.5M pa is allocated to assist the Council in achieving its improvement priorities.

It should be noted that the following allocations are indicative only, and will be subject to annual review.

Minimum and maximum figures in the table below are expressed are annual amounts. In practice these could be averages over the two years. There is no presumption towards equal phasing. It should be noted that the total of maximum figures exceeds the total available for this block by approx 50%.

Improvement Priority

Min £000

Max £000

Increase Availability of Affordable Housing (to maintain total housing programmes at c£4M pa)

750

1250

Improving the Quality of Public Transport, Roads and Pavements, and Easing Congestion

750

1000

Improving the environment for learning

750

1000

All Other Improvement Priorities

 

500

Annexe 2 - Revenue Financial Planning Targets

Revenue Target

Performance / Service Standards Target

Indicative % change over 3 years

Services

Increase

Improvement

2.0%

Public Transport

Slight Increase

Improvement

1.0%

Waste Management

No change

Improvement

0.0%

Customer Access & E Govt, Corporate Training, Major Projects and specific Services according to circumstance (contracts etc)

Tempering of growth

No change, achieved by productivity gain

-5.0%

Social Services (aim to reduce excess spending against FSS from 18% to 10%)

Tempering of growth

No change, achieved by productivity gain

-3.0%

Education (aim to reduce excess spending against FSS from 8% to 4.5%)

Reduction

No change, achieved by productivity gain

-3.0%

Most Services

Larger reduction

May involve some lowering of standards in lower priority services

-5.0%

Some Youth & Community budgets, Car Parking, Economic Development, Environmental & Consumer Services (exc. Voluntary grants), Planning Mgt & Administration and DC Administration, Emergency Mgt Unit, Legal Services, Property Services, Revenues & Benefits, some Arts budgets

Notes

     

1. Revenue targets measured in relation to constant real terms and government funding levels (latter may be linked to specific performance targets or service standards).

2. Targets expressed for the 3 year period 2004/05 - 2006/07 (hence 3% reduction is equivalent to 1% pa)

3. There is some flexibility in phasing the individual service targets between years; however the overall financial plan assumes equal phasing and so aggregated proposals, either by Director or by Executive Member, will need to reflect that equal phasing

4. Additional revenue funding will be made available to Improvement Priorities, subject to sufficient "headroom" and proper justification being made. Allocation of headroom will be considered and allocated over-and-above the above targets, when headroom is achieved.