Report to Executive
4-Monthly Performance Report
Date |
October 2004 |
Reporting Area |
Environment |
Lead Director |
Sarah Berry |
SCOPE OF REPORTING AREA
Planning Services
Economic Development
Waste Services
Environmental & Consumer Services
Energy Conservation (PALS)
Main achievements
· Local Plan revised deposit response agreed by Full Council
· Business Case for On Line Planning project developed and agreed and system ordered
· National design award for Charlotte Street Car Park project
· Revised Delegation Scheme agreed (Planning)
· Landscape Estates application dealt with successfully by officers and Committee
· City Centre Mobile infrastructure approach agreed at Executive (September)
· Tourism Service contract finally agreed and signed off with Bath Tourism Plus
· Training Services - planned closure of IT Centre went ahead smoothly
· Kerbside recycling contract extended for 2 years with ECT Recycling (branded locally as Bath & North East Somerset Community Recycling).
· Successful in bid for £20K consultancy support from the Department for Environment Food and Rural Affairs (DEFRA) local authority support unit, waste implementation programme - this is primarily to assist with improving recycling performance at the Household Waste & Recycling Centres.
· Relocation of recycling operations from Temple Cloud to Keynsham depot completed by end August.
· Domestic battery recycling added to collection rounds from end of August
· Outreach Shopmobility service trail in Keynsham.
· Number of successful prosecution including:
- Craghoppers Ltd (Trades Description Act) re. false claim of "sunsafe" leisurewear.
- Scottish and Newcastle Brewers (Food Safety Act) re. food hygiene offences at Rat and Parrot Public House (£20,000 fine).
- Numerous illegal street traders (Local Government Miscellaneous Provisions Act)
· Under age alcohol sales initiative in pubs and clubs in partnership with police using funding from Home Office.
· Gull egg oiling programme.
· Food and Trading Standards secured renewal of ISO 9002 registration.
· Clean Food Awards - new initiative; completion of inspection and assessment process plus first award ceremony.
· Coped with huge surge in pest control (wasp nests) service requests.
· Consumer Direct launched (regional call centre partnership with other south west trading standards authorities).
Planned Actions not achieved
· Planning Code of Conduct for officers and Members not yet agreed by Council
· Rural Renaissance bid submission to South West Regional Development Agency Appraisal Team
· Formal sign off of Employment Development Team integration into Economic Development Service
· Zero waste strategy timetable for production of documentation has been revised
· Finalisation of ANPR (automatic number plate recognition system) agreement with police.
· Licensing Policy (on hold awaiting government regulation; draft now subject to public consultation).
· Completion of Air Quality Action Plan.
· The Environment Park project has been delayed for 6 months whilst a thorough review of options is undertaken, for Council decision in December/January.
Development Opportunities
· Trimbridge House reception service transferred to Customer Access Programme from 1 October.
· Rethink Rubbish Waste Awareness Campaign
· Refuse & Recycling Collection Methods study
· Progress made on alternative ways of dealing with Sustainability and role of ENVOLVE
· New inter service framework and co-ordination group in place to deal with City Centre issues and Bath Western Riverside
· Potential large sums of money available through Planning Delivery Grant in next 4 years dependent on performance and IT support system
· Establishment of long term framework in City Centre linking with Western Riverside project.
· New sub-regional partnership could provide direction and focus for sub-regional working (see Corporate Projects update below)
· Discussion with potential occupants of Riverside proceeding - could yield extensive long term benefits for Keynsham.
· Development of managed workspace in conjunction with private sector operators.
· Proposals for expenditure of Public Realm funds on litter bins, gum and graffiti drafted; tourism/population fluxes research plan drafted with EnCams.
· CCTV camera provision at Southgate and Green Park.
· "Freedom from Fear" initiative - partnership with Union of Shop, Distribution & Allied Workers.
· Home Office funding for extension of underage sales campaign.
· Gambling legislation transferring responsibilities from Magistrates to local authorities.
Potential threats
· Viability of Western Riverside and impact on Local Plan process and Strategy
· ODPM requirements for Action Plan to achieve Development Control targets. Inadequate corporate and political engagement with issues on performance raised by the Office of the Deputy Manager. Potential future threat of intervention if performance not improved
· Impact of major development projects on day to day Development Control work and Local Plan process
· The new `High Hedges' legislation and potential impact on current Council resources relating to trees and nuisance
· Bath Communities Partnership - resignation of board members
· City Centre masterplanning - resource demands and impact on Local Plan Strategy if not linked to establishment of viable masterplan for Western Riverside
· Recycling targets on amber
· Annual Increase in waste arisings forecast at 5% on current tonnage forecasts.
· LATS (Landfill Allowance Trading Scheme) permit allowances - draft allocations have now been published. The high proportion of trade waste the Council deals with has significant financial implications for Bath & North East Somerset under LATS.
· Landfill Directive & Hazardous Waste Regulations affecting how cathode ray tubes can be disposed of from the Household Waste Sites - current guidance and interpretation indicates action needed within one year. This may have significant financial and operational implications on the treatment of TVs, monitors and fluorescent tubes.
· One local composting facility will no longer be available to us for a temporary period of time. This will increase operational costs through increased haulage out of the district.
· Cross Bath water quality.
· Uniform 7 software - introduction and training may have temporary negative impact on service performance.
· Increased workloads re Licensing Act 2003.
· DEFRA re inspection of authorised processes and introduction of new Solvent Emissions Regulations.
Update on Corporate Projects
Sub-Regional Working -
· Regional spatial strategy - should aim for 4 unitary authority response on Executive Forward Plan for November followed by November 15th full Council.
· Need for sub-regional partnership officer support review becoming urgent.
· Sub-regional Partnership constitution to be agreed.
· Time for appropriate Executive Member briefing to be identified to help raise awareness, help develop Bath & North East Somerset' own agenda and to take steer on forthcoming issues.
2. Reporting on targets and commitments made in the Performance Plan
Summary of Performance
Performance Targets |
Planning |
ED |
Waste |
EN&CS |
PALS |
TOTAL |
% |
RED |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
AMBER |
1 |
0 |
3 |
0 |
0 |
4 |
9 |
GREEN |
14 |
9 |
14 |
4 |
2 |
43 |
91 |
NOT KNOWN |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
TOTAL |
15 |
9 |
17 |
4 |
2 |
47 |
100% |
Ref No |
Indicator |
Best 25% of all English Councils 02/03 |
02/03 actual |
03/04 actual |
04/05 target |
04/05 estimated outturn |
Status |
Comment |
WASTE |
||||||||
82a |
% of household waste recycled |
10.09% |
19.96% |
21.08% |
23% |
21.2% |
Amber |
|
82b |
% composted |
3.73% |
6.14% |
8.43% |
11.1% |
11.2% |
Green |
|
82c |
% used to recover heat, power and other energy |
N/a |
0% |
0.11% |
0.1% |
0.1% |
Green |
|
82d |
% landfilled |
35.85% |
73.90% |
70.39% |
65.8% |
67.5% |
Amber |
|
84 |
Kg of household waste collected per head |
449kg |
500kg |
485kg |
485kg |
520kg |
Amber |
|
86 |
Cost of waste collection per household |
£25.66 |
£40.02 |
£43.34 (E) |
£45 |
£45 |
Green |
|
87 |
Cost of waste disposal per tonne |
£29.61 |
£46.97 |
£51.51 (E) |
£60.83 |
£60.83 |
Green |
|
Local 1 |
Cleanliness standards of streets and public open spaces maintained by B&NES |
N/a |
71% |
69% |
72% |
72% |
Green |
|
199a |
% of land that is assessed as being clean |
N/a |
10% |
29% |
29% |
28% |
Green |
Sum of 199 a and 199 b = compliant |
199b |
% of land that is assessed as having light litter |
N/a |
75% |
44% |
47% |
51% |
Green |
|
199c |
% of land that is assessed as having significant litter |
N/a |
10% |
16% |
16% |
14% |
Green |
|
199d |
% of land that is assessed as having heavy litter |
N/a |
5% |
10% |
8% |
7% |
Green |
|
91 |
% served by a kerbside collection of recyclables or within 1 kilometre of a recycling centre |
99% |
100% |
100% |
100% |
100% |
Green |
|
Local 86 |
Percentage of graffiti cleared from public buildings within 2 days of reporting |
N/a |
New |
65% |
80% |
90% |
Green |
|
Local 87 |
Average time taken to remove fly-tips (days) |
N/a |
3.41 |
1.73 |
2 |
2 |
Green |
|
ENVIRONMENTAL HEALTH & TRADING STANDARDS |
||||||||
179 |
% of standard searches carried out in 10 working days |
100% |
100% |
100% |
100% |
100% |
Green |
|
166a |
Score against a checklist of enforcement best practice for environmental health |
89.00% |
89.00% |
96.5% |
90% |
90% |
Green |
|
166b |
Score against a checklist of enforcement best practice for trading standards |
94.95% |
89.00% |
96.5% |
90% |
90% |
Green |
|
Local 6 |
% of environmental health, trading standards and licensing customers rating service as good, very good or excellent |
N/a |
92% |
94% |
92% |
92% |
Green |
|
BUILDING REGULATIONS |
||||||||
Local 7 |
% of Building Regulations Applications appraised within 3 weeks |
N/a |
92% |
89% |
95% |
95% |
Green |
|
LOCAL ECONOMY |
||||||||
Local 12 |
Long term unemployment as a percentage of total unemployment |
N/a |
8.0% |
9.0% |
9.0% |
6 month average = 9.3 Aug = 8.8 |
Green |
|
Local 13 |
Average level of unemployment in 4 key wards |
N/a |
408 |
390 |
420 |
6 month average = 359 Aug = 345 |
Green |
|
Local 14 |
Numbers of existing businesses advised |
N/a |
380 |
403 |
420 |
420 193 to date |
Green |
|
Local 17 |
Average annual room occupancy in hotels and guest houses |
N/a |
63.5% |
55% |
58% |
57% |
Green |
|
Local 18 |
Average length of stay in hotels and guest houses (nights) |
N/a |
2.0 |
1.7 |
1.7 |
1.9 |
Green |
|
Local 19 |
Tourism web-site users ('000s) |
N/a |
272 |
355 |
400 |
400 |
Green |
|
Local 20 |
Disadvantaged teenagers assisted/trained |
N/a |
84 |
89 |
90 |
90 |
Green |
Targets to be reviewed following LSC contract negotiations |
Local 21 |
Number of young people accessing work based learning through Modern Apprenticeship programme |
N/a |
56 |
80 |
90 |
90 |
Green |
Targets to be reviewed following LSC contract negotiations |
PLANNING & DEVELOPMENT |
||||||||
200b |
If No, are there proposals to publish local plan within 3 years ? |
N/a |
Yes |
Yes |
Yes |
Yes |
Green |
|
106 |
% of new homes built on previously developed land Depends on the number and type of applications received each year. On average we expect 55% |
91.68% |
77.61% |
75% (E) |
60% |
65% |
Green |
Estimated on anticipated take up of brownfield sites |
Local 56 |
Planning cost per application (£) |
N/a |
£638 |
£655 (E) |
£683 |
£680 |
Green |
|
109a |
% of planning applications determined within Govt. targets - % within 13 weeks - major developments |
55.00% |
33.30% |
22% |
40% |
50% |
Green |
The estimated outturn is based on latest figures. However the estimate can change significantly due to the relatively small number of applications. |
109b |
- % within 8 weeks - minor developments |
63.66% |
57.40% |
58% |
60% |
59% |
Amber |
Whilst we are currently below target it is anticipated that the Improvement Action Plan will assist in it being reached. |
109c |
- % within 8 weeks - other developments |
80.51% |
66.45% |
70% |
75% |
75% |
Green |
|
204 (New) |
% of appeals allowed against the authority's decision to refuse planning applications |
N/a |
N/a |
30% |
35% |
25% |
Green |
|
205 (New) |
Quality of service checklist |
N/a |
N/a |
New |
72% |
83% |
Green |
|
Local 57 |
% of applications determined within 8 weeks |
N/a |
65% |
67% |
70% |
71% |
Green |
|
Local 58 |
% of delegated applications determined within 8 weeks The marginal reduction in performance is as a result of more complex applications being delegated to officers. |
N/a |
77% |
75% |
78% |
80% |
Green |
|
Local 70 |
% applications of works to trees in conservation areas dealt with within 6 weeks |
N/a |
87% |
90% |
85% |
87% |
Green |
|
Local 71 |
% of applications for works to trees and woodlands covered by Tree Preservation Orders dealt with within 8 weeks |
N/a |
88% |
85% |
85% |
89% |
Green |
|
Local 72 |
% of approved applications subject to negotiations and added value |
N/a |
35% |
37% |
37% |
38% |
Green |
|
C1 |
Maximising the use through the planning system of contribution to affordable housing from developers by adopting Supplementary Planning Guidance on affordable housing and by ensuring that it is a key feature within the Local Plan |
N/a |
N/a |
N/a |
Do It |
Completed |
Green |
|
C4 |
Review domestic waste collection regimes, methodologies and frequencies |
N/a |
N/a |
N/a |
Do It |
On target |
Green |
Draft report to be produced in October |
C5 |
The establishment of new City Centre Governance arrangements to tackle cross-cutting issues such as:- · Delivery regime for commercial vehicles · Access & Traffic flows in and around the core city centre · Prioritised options for enhancement to the city centre environment · Feasibility plans and estimates for implementing the highest priority project |
N/a |
N/a |
N/a |
Do It |
Achieved |
Green |
Governance arrangements established. Work on cross cutting issues commenced. |
C7 |
Introduction of a scheme to empower nominated staff to impose fines on members of the public who drop litter in public places |
N/a |
N/a |
N/a |
Do It |
On target |
Green |
Draft report currently with legal for comment |
180a(i) |
Energy consumption of Council properties - electricity |
85% |
69% |
68%(E) |
67% |
100% |
Green |
Not a statutory requirement for 2003/04 - Best Estimate provided. Government has changed basis of measurement since 2003/04 targets were set. Achievement of a lower percentage is improvement. |
180a(ii) |
78% |
89% |
88%(E) |
87% |
96% |
Green |
See above |
3. Equalities Targets
Service Area |
% of staff from BME communities |
% of staff considering themselves disabled |
Comment |
||
Actual |
Target |
Actual |
Target |
||
ECS |
2.4% |
2.4% |
1.2% |
1.2% |
|
Planning |
1.3% |
3% by 2008 |
5.67% |
Remain at above 5% |
The limited turnover of staff impacts on the ability to achieve the corporate targets set regarding BME communities. The Service is working with Human Resources to examine the recruitment process to maximise the potential of reaching all communities. |
Economic Development |
6.5% |
4% |
0% |
4% |
|
Waste Services |
0% |
To achieve 1% by 2005 |
0% |
To achieve 1% by 2005 |
The low level of turnover and number of staff within the team impacts on the ability to achieve the corporate targets set. The service is working with Human Resources to examine the recruitment process to maximise the potential of reaching all communities. |