1 THE ISSUE
1.1 This report introduces the Four-monthly Environment Peformance Report, which is attached as Appendix 1.
2 RECOMMENDATION
2.1 Consider and note the contents of this report
3 FINANCIAL IMPLICATIONS
3.1 Included in the report.
4 THE REPORT
4.1 As part of the Council's performance management framework the Strategic Director (Economic & Environmental Development) is required to submit an Environment Four-monthly performance to the Directors' Group. This report is also submitted to the relevant Portfolio Executive Members and finally a meeting of the Executive Council.
4.2 The Environment Four monthly Performance Report is attached as Appendix 1.
Contact person |
Clive Thomas, Strategic Director (Economic & Environmental Development) |
Background papers |
none |
Appendix 1
Report to Executive
4-Monthly Performance Report
Date |
8 September 2003 |
Reporting Area |
Environment |
Lead Director |
Clive Thomas |
SCOPE OF REPORTING AREA
Planning
Environment & Consumer Services
Economic Development inc. Tourism
Waste
Refuse
Cleansing
1. Progress / Issue Reporting |
|||||
Progress Made |
Issues to be addressed |
Who |
By When |
||
LeadershipUpdates on previous report |
· Planning Best Value Review - Action Plan agreed by Steering Group and Overview and Scrutiny. To be reported to relevant portfolio holders in September. |
· The election and subsequent timescales in formalising political decision making has slightly delayed the process |
DD/FH |
September |
|
· Training for new Planning Committee Members. |
· Three training sessions held since the election. A future programme being drawn up. |
DD/EF |
September |
||
· Open Planning Forum (private sector) still happening on regular basis. |
· Forum updated regarding as potential for future Area Committee arrangements. |
DD |
On-going |
||
· Regular liaison meetings with Property Services still happening. |
· Resulted in better relationship between Services and resultant effectiveness of consultative liaison. |
DD/EF |
On-going |
||
· Meeting and workshop held with national agents to discuss procurement issues. |
· The production of framework agreements within the Best Value Action Plan (to help quick procurement of resources). |
DD |
November |
||
· Gull egg oiling initiative |
· Successful `season' building on 2002 progress. |
EP Manager |
Done |
||
· Tourism Company near completion |
· Service Level Agreement to be finalised |
Bill Cotton |
End Sep 03 |
||
· Chief Executive & Marketing Manager appointed |
|||||
· DEFRA funded projects: Plastics expansion was fully implemented form April 03 across district. |
· Funding for plastics expansion to be included in the financial planning process |
RR |
Late Sept |
||
· Bulky Waste & WEEE: Retail outlet at Ham Gardens progressing well from April 2003 |
· Viability after March 2003 for SOFA staff funding |
KH |
Late Oct |
||
Waste Best Value Review Action Plan incorporated into Business Plan & final version produced June 03. |
· Implementation of Business Plan actions |
RR |
Ongoing |
||
· Pioneering Rethink Rubbish campaign continuing with extensive advertising and programme of events. |
· LTCS funding ends March 2004. Alternative Defra funding to be pursued (awaiting notification of WRAP funding programme) |
KH |
Late Oct |
||
· Car Clear project - will continue within existing budget constraints. |
· Year 2 funding from Police & Fire Authorities not available, but ODPM has funded police coordination post. Council continuing with scheme within existing budgets. |
KH |
Late Oct |
||
· Environment Park - External Advice on procurement contract documentation and strategic partner agreement - contracts placed with specialist consultants |
· Ensure key milestones are met |
RR |
Ongoing March 2004 |
||
· Environment Park - Environmental Impact Scoping brief lodged with Planning Authority |
Done |
||||
· Railtrack unable to undertake feasibility study on the construction of the underline bridge required for Environment Park site access. · Specialist consultant appointed on advice of Network Rail |
· Ensure proposed rail occupation for construction matches development critical path. |
RR |
Late Sept |
||
· Regional Development Agency responded listing potential funding initiatives |
· Economic Development taking the lead. |
DW |
Late Sept |
||
LeadershipNew items |
· Way forward agreed with a view to increasing liaison with Business Community. |
· To address the key stakeholder views which have come out of the Best Value Review. |
DD |
December |
|
· Radical proposals for D.C. structure out for consultation, together with flexibility and costings if increased number of committees for planning. |
· Structure to meet challenges of new planning system and issues raised through Best Value Review. |
DD |
On-going |
||
· Scanning and back scanning projects identified through the PARIS partnership as high priority. |
· Essential for the Planning Service to develop and achieve e-gov. targets. |
DD |
On-going |
||
· Building Design Award Scheme - winners entered in national competition |
· Bellway Homes win house builders category |
BC Manager |
Done |
||
· Chartermark for CCTV |
· Achievement (1st in Country) |
SMLC Manager |
Done |
||
· Community Support Network newsletter used by DTI as exemplar. |
· Maintain quality and support other LAs seeking to develop |
FTS Manager |
Ongoing |
||
· Rural renaissance bid being prepared on behalf of sub region |
· Ensure cross-authority support |
Bill Cotton |
End Apr 04 |
||
PeopleUpdates on previous report |
· Recycling Officer in post from 28th April 2003 |
On-going prioritisation of workload |
KH |
Ongoing |
|
· Project Manager for Green Waste & Cardboard in post from 19th May. Admin to be covered from within DS Admin Team |
On-going prioritisation of workload |
KH |
Ongoing |
||
· Manager on maternity leave from June 2003 - cover appointed & resources reallocated |
Resources for expanding workloads |
RR |
Ongoing |
||
· Project Development Officer in post from July 2003 |
Review progress during probation period |
RR |
Ongoing |
||
PeopleNew items |
· Revision of ECS Health and Safety Manual |
· Completion of risk assessment reviews |
HoS |
September 2003 |
|
· Pest Control service relocation from Bath to Radstock Road Depot |
· Logistical - service delivery focus in Bath area |
EP Manager |
Ongoing |
||
· Training Services staff review underway |
· Recruitment of key new management post |
Joy Townley |
End Oct |
||
· Secondment of 2 SED staff to Norton Radstock Regeneration Company |
|||||
Partnership & Resources New items |
· Agreement with police on operational resource for ANPR using CCTV network |
· Contract signing |
SMLC Manager |
November 2003 |
|
Policy and Strategy Updates on previous report |
· The Local Plan now agreed by Council for 2nd Deposit consultation. |
· This will help achieve robustness of planning decisions. |
DD/VT |
July |
|
· Advice received to indicate that it is essential to progress Local Plan to Inquiry. |
· Important for public perception of plan process and to properly test key policies. |
DD/VT |
May 2004 |
||
· World Heritage Site Management Plan agreed by Executive. |
· Funding required for implementation issues. |
VT |
November |
||
· Western Riverside SPG approved by Full Council. |
· A key stage in ensuring a sustainable comprehensive high quality development for this area. |
VT |
July |
||
· Landscape character appraisal now published and on website. |
· Essential background information embodied in Local Plan to aid proper decision making. |
VT |
May |
||
· High profile Zero Waste consultant appointed. |
· Council Executive approval key timetable dates |
RR |
Early September |
||
· Public Service Agreements approved August 2003 |
· Ensure funding committed within approved timescale. |
RR |
Ongoing |
||
Policy and Strategy New items |
· Officer engagement in the community strategy to ensure linkage between evolving issues and Land Use Planning. |
· Essential for the linkages to be made as the Local Plan is a key vehicle for enabling implementation. |
VT |
On-going |
|
· Officer engagement in Customer Access Programme. |
· Important to ensure Service objectives enabled and not prejudiced by corporate programme. |
DD |
On-going |
||
· Licensing Act - major changes to alcohol and entertainment licensing |
· Licensing Forum leading to establishment of Licensing Policy |
EML Manager |
January 2004 |
||
· Bath Community Partnership Delivery Plan agreed by RDA and Council |
· Ensuring projects are developed & delivered |
Bill Cotton |
End March 04 |
||
Resources Update on previous report |
· Planning Workload fund still being fully used as a result of highest ever number of applications being submitted. |
· Important to try and ensure a supply of alternative arrangements to cope with high workload and leavers. |
DD |
On-going |
|
· Long term sickness problems reported previously with the enforcement service should shortly be resolved. |
· This has impacted on overall performance of the D.C. Services. |
DD |
September |
||
· The planning delivery grant awarded is being invested in I.T. support systems - the projects identified through the PARIS Partnership. |
Investment required to improve customer satisfaction and Service delivery issues. Early consideration by Business Improvement Process critical. |
DD |
March 2004 |
||
Partnership and Resources New Items |
· The Wildthings Partnership has been successful in a bid relating to a Batscape Project. This has procured £167,000 for an investment of under £10,000. |
· This represents real value for money and the project should ultimately aid policy development and the decision making process. |
DD |
May |
|
Processes Update on previous report |
· New Planning Services delegation scheme has now been implemented (beginning of May) with a view to moving towards government targets. |
· This is important to help improve performance, and reduce the workload of committees. |
DD |
May |
|
· The Delivery Contract proposed continues to be used. |
· Essential to counter criticism of failure to deal with some major applications within 13 weeks. |
DD |
May |
||
· Enforcement Policy now on website and being implemented. |
· Vital to achieve prioritisation of issues and help manage workloads. |
DD/EF |
May |
||
· New Code of Conduct for Planning Members not yet adopted by Full Council. |
· Essential with regards to probity, transparency and perception of democratic process by the public. |
DD |
July |
||
· Development Control Charter now approved - soon to be put on website. |
· Sets standards of service delivery for the public. |
DD |
July |
||
· Licensing Committee member training provided in June. |
· Further training session in September |
HoS |
September 2003 |
||
Process New Items |
· New Planning filing system developed by Staff Group to aid data retrieval and provide platform for integration with new software. |
· Essential to ensure total harmonisation of process and procedures and to reduce inefficiencies in data retrieval. |
HS |
September |
|
· Audit of Development Control Process carried out by Internal Audit and Actions agreed. |
· The processes in place were previously found to be sound. A few minor adjustments relating to ordering etc. agreed and other issues picked up in Best Value Review. |
DD/EF |
June |
||
· Designing Out Crime protocol being developed in partnership with the Police. |
· This document details a protocol between the Local Authority and the Police with regards to consultation and issues to be considered at the application stage. |
DD/EF |
September |
||
· Illegal encampment at former Clarks factory site |
· Joint action with police to secure removal |
EP Manager |
Done |
||
· Health and Safety enforcement programme |
· Build on two successful prosecutions |
EP Manager |
Ongoing |
||
· Prosecution of illegal street traders (9 in first quarter) |
· Continue with formal action |
EML Manager |
Ongoing |
2. Reporting on targets and commitments made in the Performance Plan
Summary of Performance
Performance Targets |
Planning |
EN&CS |
S&ED |
Waste |
PALS |
TOTAL |
% |
RED |
2 |
0 |
0 |
0 |
0 |
2 |
3.5% |
AMBER |
1 |
2 |
4 |
6 |
0 |
13 |
22% |
GREEN |
9 |
4 |
4 |
17 |
2 |
36 |
61% |
NOT KNOWN |
6 |
0 |
2 |
0 |
0 |
8 |
13.5% |
TOTAL |
15 |
6 |
10 |
23 |
2 |
59 |
100 |
* 9 not currently able to be carried out (annual survey; Voicebox; national database query)
Ref No |
Indicator |
Best 25% of all English Councils 01/02 |
01/02 actual |
02/03 actual |
03/04 target |
03/04 estimated outturn |
Status |
Comment |
82a |
% of household waste recycled |
11 |
18 |
20 |
22 |
21 |
Amber |
82 a, b, d: Forecasts based on 1st Qtr and previous year's seasonality |
82b |
% household waste composted |
5 |
5 |
6 |
11 |
9 |
Amber |
· Full impact of Garden Waste & Cardboard scheme & · PSA initiatives at HWRCs to take effect |
82c |
% household waste used to recover heat, power and other energy |
0 |
0 |
0 |
0 |
0 |
Green |
|
82d |
% household waste landfilled |
79 |
77 |
74 |
67 |
70 |
Amber |
Forecasts based on 1st Qtr and previous year's seasonality |
84 |
Kg of household waste collected per head |
487 |
492 |
500 |
500 |
490 |
Green |
Forecasts based on 1st Qtr and previous year's seasonality |
86 |
Cost of waste collection per household (cost has risen because we now include the cost of recycling) |
27.61 |
35.17 |
40.02 |
43.30 |
43.30 |
Green |
2002/03 figure amended to actual 2003/04 target revised to include recycling collection costs |
87 |
Cost of waste disposal per tonne |
28.97 |
49.95 |
46.97 |
52.90 |
51.19 |
Green |
2002/03 figure amended to actual |
88 |
Number of household waste collections missed per 100,000 |
25 |
211 |
161 |
130 |
106 |
Green |
|
Local 88 |
Number of missed bins collected by the end of the next working day |
N/a |
87 |
90.07 |
89 |
91.6% |
Green |
|
89 |
% of people satisfied with cleanliness standards |
71 |
N/a |
Not measured |
71 |
N/a |
Green |
Voicebox surveys- to be arranged |
199a (new) |
% of land that is assessed as being clean |
N/a |
N/a |
10 |
10 |
42 |
Amber |
199 a - d: Queries to be resolved over operation of National Database |
199b (new) |
% of land that is assessed as having light litter |
N/a |
N/a |
75 |
75 |
44 |
Green |
199 a - d: Queries to be resolved over operation of National Database |
199c (new) |
% of land that is assessed as having significant litter |
N/a |
N/a |
10 |
10 |
11 |
Amber |
199 a - d: Queries to be resolved over operation of National Database |
199d (new) |
% of land that is assessed as having heavy litter |
N/a |
N/a |
5 |
5 |
3 |
Green |
199 a - d: Queries to be resolved over operation of National Database |
Local 1 |
Street Cleanliness standards (Tidy Britain Group's CIMS index) |
N/a |
N/a |
71 |
72 |
See comment |
Green |
Annual survey - October/November |
90a |
% expressing satisfaction with - household refuse collection facilities |
90 |
N/a |
Not measured |
90 |
See Comment |
Green |
90 a -c: Voicebox surveys to be arranged |
90b |
% expressing satisfaction with recycling facilities |
73 |
N/a |
Not measured |
77 |
See comment |
Green |
90 a -c: Voicebox surveys to be arranged |
90c |
% expressing satisfaction with household waste & recycling centres |
77 |
N/a |
Not measured |
77 |
See Comment |
Green |
90 a -c: Voicebox surveys to be arranged |
91 |
% served by a kerbside collection of recyclables or within 1 kilometre of a recycling centre |
100 |
100 |
100 |
100 |
100 |
Green |
|
Local 87 |
Average time taken to remove fly-tips (days) |
N/a |
1.52 |
3.41 |
2.00 |
1.75 |
Green |
|
180a(i) (new) |
Energy consumption of Council properties - electricity |
N/a |
N/a |
101 |
100 |
100 |
Green |
No indication that target will not be hit |
180a(ii) (new) |
Energy consumption of Council properties - fossil fuels |
N/a |
N/a |
96 |
95 |
95 |
Green |
No indication that target will not be hit |
166a |
Score against a checklist of enforcement best for environmental health |
76 |
70 |
90 |
90 |
90 |
Green |
|
166b |
Score against a checklist of enforcement best for trading standards |
85 |
70 |
89 |
90 |
90 |
Green |
|
Local 6 |
% of environmental health, trading standards and licensing customers rating service as good, very good or excellent |
N/a |
N/a |
92 |
92 |
92 |
Green |
|
Local 7 |
% of Building Regulations Applications appraised within 3 weeks |
N/a |
N/a |
92 |
94 |
90 |
Amber |
Unlikely to recover form combination of staff shortage and unprecedented service demand in first quarter |
Local 12 |
Long term unemployment as a percentage of total unemployment |
N/a |
N/a |
8 |
8 |
7 |
Green |
Result of low levels of unemployment & Job Centre Plus initiatives |
Local 13 |
Reduction in the level of unemployment in key wards |
N/a |
4 |
4.1 |
3.3 |
4 |
Amber |
Total unemployment in target wards has reduced on a monthly basis since February 2003. But seasonal trends may affect eventual outturn. |
Local 14 |
Numbers of existing businesses advised |
N/a |
N/a |
380 |
370 |
400 |
Green |
|
Local 15 |
Number of potential new businesses provided with training |
N/a |
New |
248 |
180 |
175 |
Amber |
Venues of Training to be reviewed to increase attendances from B&NES businesses |
Local 17 |
Average annual room occupancy in hotels and guest houses |
N/a |
N/a |
63.5 |
57 |
NK |
NK |
No data yet available. Collection of stats is outside our control and produced in arrears. |
Local 18 |
Average length of stay in hotels and guest houses (nights) |
N/a |
N/a |
2 |
1.9 |
N/K |
NK |
No data yet available. Collection of stats is outside our control and produced in 3 months arrears. |
Local 19 |
Tourism web-site users ('000s) |
N/a |
New |
272 |
300 |
272 |
Amber |
|
200a (new) |
Do we have a local plan that has been adopted in the last 5 years? |
N/a |
New |
No |
No |
No |
Red |
The Local Plan is subject to a clear programme which has been agreed with GOSW. GOSW require this Authority to carry on with the current Plan. |
200b (new) |
If No, are there proposals to publish within 3 years? |
N/a |
New |
Yes |
Yes |
Yes |
Green |
The Local Plan should be adopted in the year 05/06 |
106 |
% of new homes built on previously developed land |
91 |
70 |
74 |
55 |
Too early to estimate |
NK |
There is only a finite amount of brown-field sites and the targets are contained in the Local Plan based on the Urban Capacity Study. |
107 |
Planning cost per head of population (£) |
7.3 |
17.14 |
17.63 (e) |
17.63 |
Too early to estimate |
NK |
The target has previously been to reduce costs. However, the Government are awarding more money to planning authorities, and the expectations are that the figure will rise. |
Local 56 |
Planning cost per application (£) |
£701 (Average) |
731 |
638 |
683 |
Too early to estimate |
NK |
See above. |
109a (new) |
% of planning applications determined within Govt. targets - % within 13 weeks - major developments |
N/a |
27 |
33 |
35 |
30% |
Red |
The Government have been informed by the Council of the difficulties of achieving targets in this category. |
109b (new) |
% of planning applications determined within Govt. targets - % within 8 weeks - minor developments |
N/a |
55 |
58 |
59 |
60% |
Green |
|
109c (new) |
% of planning applications determined within Govt. targets - % within 8 weeks - other developments |
N/a |
66 |
68 |
70 |
70% |
Green |
|
Local 57 |
% of applications determined within 8 weeks |
73 |
63 |
65 |
68 |
68% |
Green |
|
Local 59 |
% of appeals dismissed |
N/a |
68 |
58 |
65 |
65% |
Green |
|
111 |
% of applicants and those commenting on planning applications satisfied with the service received |
N/a |
65 |
81 |
82 |
No data |
NK |
National survey to be carried out in the Autumn. |
188 |
% of decisions delegated to officers |
N/a |
78 |
79 |
90 |
84% |
NK |
It is probably too early to see full impact of new delegation scheme. The 84% relates to May-July. |
Local 58 |
% of delegated applications determined within 8 weeks |
N/a |
63 |
77 |
78 |
76% |
Amber |
|
112 |
% score against a checklist of planning best practice |
70 |
80 |
8 0 |
80 |
80% |
Green |
|
Local 70 |
% applications of works to trees in conservation areas dealt with within 6 weeks |
N/a |
85 |
87 |
80 |
82% |
Green |
|
Local 71 |
% of applications for works to trees and woodlands covered by Tree Preservation Orders dealt with within 8 weeks |
N/a |
85 |
88 |
80 |
82% |
Green |
|
Local 72 |
% of approved applications subject to negotiations and added value |
N/a |
N/a |
35 |
36 |
Too early to estimate |
NK |
|
179 |
% of standard searches carried out in 10 working days |
100 |
100 |
100 |
100 |
100 |
Green |
|
QL5 |
Develop proposals for an Environment Park to strive to move towards our zero waste aspirations and meet ambitious recycling targets |
Do It |
Green |
Adjustments to Master Plan under consideration. Long term project. |
||||
HS4 |
Develop a Consumer Network in partnership with other councils and consumer groups |
Do It |
Amber |
Potential partners proceeding slower than expected. |
||||
EC2 |
Produce a Keynsham Town Centre Action Plan with includes events and environmental improvements in partnership with Keynsham Town Council |
Do It |
Done |
Green |
||||
EC3 |
Complete an employment land study, influence preparation of the local plan, promote appropriate premises for business and improve the property database |
Do It |
Done |
Green |
Findings of Study used to draw up revised employment land policies for 2nd draft deposit Local Plan |
|||
EC4 |
Improve public conveniences in Bath City Centre |
Do It |
Green |
Three Phase Plan being prepared. Automatic Toilet Programme through PSA funding. |
||||
EC5 |
Produce a corporate Sustainability Action Plan |
Do It |
Amber |
Draft Action Plan is going through the O&S process |
||||
EC6 |
Through the Planning Services Best Value Review investigate and implement improved engagement with the Business Community |
Do It |
Green |
This is being progressed through the Open Planning Forum and also in partnership with Officers in SEDS. New information leaflets are being produced to help the business community understand the planning process |
3. Equalities Targets
Service Area |
% of staff from BME communities |
% of staff considering themselves disabled |
Comment |
||
Actual |
Target |
Actual |
Target |
||
Planning Services |
0% |
3% by 2008 |
5.6% |
Remain at above 5% |
The limited turnover of staff impacts on the ability to achieve the corporate targets set regarding BME communities. The Service is working with Human Resources to examine the recruitment process to maximise the potential of reaching all communities. |
Environmental & Consumer Services |
2.4% |
2.4% |
1.2% |
1.2% |
The limited turnover of staff impacts on the ability to achieve the corporate targets set. The service is working with Human Resources to examine the recruitment process to maximise the potential of reaching all communities. |
Sustainability & Economic Development |
3.8 |
Maintain current level |
3.8 |
To achieve 5% by 2005 |
|
Waste Services |
0 |
To achieve 1% by 2005 |
0 |
To achieve 1% by 2005 |
The limited turnover and number of staff impacts on the ability to achieve the corporate targets set. The service is working with Human Resources to examine the recruitment process to maximise the potential of reaching all communities. |