Bath Quays North

This decision relates the contractual agreements for the provision of electrical infrastructure works by utility providers at Bath Quays North (BQN). Approval is sought to novate the “Council/Western Power Distribution (WPD), Point of Connection agreement (PoC)” to “PowerOn Connections Ltd (PowerOn)”.

Novation has been recommended by the Councils development partner (L&G). The novation will allow PowerOn to have sole responsibility for the management and co-ordination of the electrical installation direct with WPD. The novation will also place control of electrical supply with PowerOn.

PowerOn has been appointed by the Council for the main electrical infrastructure works. The appointment arises through the BQN Early Works agreement and is managed by L&G and their development manager.

Background:
The Council has appointed L&G as its development partner for the Bath Quays North (BQN) regeneration development. To secure the electrical capacity for BQN, a point of connection (PoC) was procured with WPD. During the course of 2021 and 2022, PowerOn have been engaged by L&G to execute off site preparatory works, the installation of a temporary substation and diversionary works co-ordination. It is recommended that the WPD PoC agreement is now novated to PowerOn to allow direct management control of WPD by PowerOn.

Novation Contractual Matters.
Novation of the WPD PoC agreement to PowerOn will take place using WPD standard terms of contract. The novation agreement has been signed by PowerOn and requires the signatures of the Council and WPD.

Additional assurances have been agreed between the Council and PowerOn and recorded in a side letter agreement. The side letter agreement is to be executed simultaneously with the Council/WPD/PowerOn novation.


Decision type: Non-key

Decision status: Approved

Notice of proposed decision first published: 22/09/2022

Decision due: 14 Sep 2022 by Director of Regeneration & Housing

Contact: Simon Martin, Director of Capital & Housing Delivery 01225 477000 Email: Simon_martin@bathnes.gov.uk Tel: 01225 477407.