York Street - Phase 2 Vault Repairs: Additional Budget
To fund the completion of committed highways
works to York Street to replace waterproofing above the vault and
reconstruct the road to complete the repairs and reduce risk of any
premature failure of the vault in the future. At the same time to
improve the public realm in York Street between Kingston Parade and
Stall street and the northern section of Swallow Street which
included resurfacing in in high-quality natural stone.
Decision type: Non-key
Decision status: Approved
Notice of proposed decision first published: 21/09/2022
Decision due: 21 Sep 2022 by Director of Sustainable Communities
Contact: Maria Newton, Group Accountant Email: maria_newton@bathnes.gov.uk 01225 477358 Email: maria_newton@bathnes.gov.uk Tel: 01225 477358.