Decision details
Aspire Academy Expansion - Wellsway MAT
Decision Maker: Director of Education, Inclusion and Childrens Safeguarding
Decision status: Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
Under section 14 of the Education Act 1996,
Local Authorities have a statutory duty to ensure that there are
sufficient schools for primary and secondary education in their
areas and for securing that special educational provision is made
for pupils who have special educational needs and disability
(SEND).
The Council's SEND priorities are set out in the SEND Education
Strategy and Action Plan 2018-21 and have three main aims:
• Improve capacity, reach and delivery of SEND education
support services, based on local need
• Support inclusion improvement and sector-led co-ordination
of SEND teaching and practice for all children with SEND age 0
– 25 years
• Deliver local education SEND placement sufficiency and
reduce unsustainable costs driven by out of county placements and
travel.
The capital project will fund works to expand The Aspire Academy to
provide up to 120 places for children with special educational
needs from primary age through to 6th Form.
The project will expand the Aspire Academy by remodelling and
extending the former Bath Studio School site at Frome Road, Bath to
create additional specialist school places for ambulant
pupils.
The project will provide much needed additional SEND places for
children in the Bath and North East Somerset catchment locally and
allow them to be educated in their local communities and not
travel, in some cases long distances to school. Additional local
places at Aspire Academy would reduce the rising financial cost to
the Local Authority and support the priorities set out in the SEND
Education Strategy 2018-2021.
Decision:
To fully approve capital amounting to
£2,198,947 from the provisional capital programme item Basic
Needs - School Improvement/Expansion of
£15,366,000.
Alternative options considered:
None. This project is part of a wider
Education Strategy to improve sufficiency and reduce rising costs
as demand for support for children with SEND increases. Following
the closure of Bath Studio School 2019-20 it is felt that this is a
deliverable project utilising an existing school site within the
Wellsway Multi Academy Trust. The project meets the Council's
requirements for SEND provision within the area and the required
timescales. The project meets the priorities of the SEND Education
Strategy and Action Plan 2018-2021.
Publication date: 16/11/2020
Date of decision: 16/11/2020